3414 W 17TH ST 90019
Certificate Information: 3414 W 17TH ST 90019
- Application / Permit
- 23016-10000-14807
- Plan Check / Job No.
- B23LA08489
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: 1) VERIFICATION OF WORK PROPOSED UNDER GARAGE TO ADU CONVERSION OBTAINED UNDER SEPARATE PERMIT # 23016-10000-15602 MEETS THE MINIMUM REQUIREMENTS OF DIV. 93. USING SHEARWALLS ALONG THE NORTH, WEST AND EAST SIDE OF THE BUILDING (TWO NEW ADU'S ARE PROPOSED WHICH WILL ELIMINATE 4 EXISTING PARKING STALLS). CERTIFICATE OF COMPLIANCE FOR SOFT STORY SHALL NOT BE ISSUED TILL CERTIFICATE OF OCCUPANCY FOR ADU PERMTI IS OBTAINED
- Permit Issued
- Issued on 5/9/2024
- Issuing Office
- Current Status
- Issued on 5/9/2024
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | JESSE VIDUYA |
| Corrections Issued | 6/8/2023 | JESSE VIDUYA |
| Quality Review Completed | 6/20/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/24/2023 | JESSE VIDUYA |
| Applicant returned to address corrections | 12/14/2023 | JESSE VIDUYA |
| Applicant returned to address corrections | 4/12/2024 | JESSE VIDUYA |
| Plan Check Approved | 4/25/2024 | JESSE VIDUYA |
| Issued | 5/9/2024 | APPLICANT |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 8/25/2023 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 4/25/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Hershel Construction Inc; Lic. No.: 780613-B | , |
| Engineer | Alson,, Ken; Lic. No.: NA41697 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/3/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/9/2024 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 10/2/2024 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Final | 12/11/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 12/11/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 12/11/2024 | Corrections Issued | DARRYL ARNOLD |