555 S FLOWER ST 27th Floor 90071

Certificate Information: 555 S FLOWER ST 27th Floor 90071

Application / Permit
23016-10000-14368
Plan Check / Job No.
B23LA08307
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT TO (E) OFFICE ON 27TH FLOOR.
Permit Issued
Issued on 1/17/2024
Issuing Office
Current Status
Permit Finaled on 5/28/2025

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 SERGIO GUTIERREZ
Corrections Issued 5/15/2023 SERGIO GUTIERREZ
Quality Review Completed 5/16/2023 RODOLFO ARIAS
Plan Check Approved 1/17/2024 SERGIO GUTIERREZ
Issued 1/17/2024 APPLICANT
Permit Finaled 5/28/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

Miscellaneous Cleared 5/25/2023 YINGSHI HUANG
Miscellaneous Cleared 5/25/2023 YINGSHI HUANG
ZI Cleared 5/25/2023 YINGSHI HUANG
ZA Case Cleared 5/30/2023 GRACIELA ACOSTA
DAS Clearance Cleared 7/28/2023 Ricardo Ramirez Solis
Fire Marshal Fire Life Safety Cleared 12/28/2023 PEJMAN NOORI

Contact Information

Architect Schmalz,, William James; Lic. No.: NA29735       ,
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Wilkerson,, Ryan Lee; Lic. No.: NA4728       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 6/3/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 7/9/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/18/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/17/2024 Not Ready for Inspection PAUL BAZERKANIAN
T-Bar Ceiling 10/17/2024 Not Ready for Inspection PAUL BAZERKANIAN
Light Gage Steel Frame 10/21/2024 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 10/25/2024 Partial Approval PAUL BAZERKANIAN
Special/Order Compliance 10/25/2024 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 12/5/2024 Partial Approval PAUL BAZERKANIAN
Structural Steel Frame 1/29/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 2/4/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 2/6/2025 Partial Approval PAUL BAZERKANIAN
Final 5/28/2025 Permit Finaled PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 5/28/2025 Approved PAUL BAZERKANIAN