2269 W WASHINGTON BLVD unit 9 90018

Certificate Information: 2269 W WASHINGTON BLVD unit 9 90018

Application / Permit
23016-10000-14211
Plan Check / Job No.
B23LA08259
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Eplan Convert existing storage to new ADU per GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
Issued on 8/11/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/8/2023 DANIEL SANJUAN
Corrections Issued 5/9/2023 DANIEL SANJUAN
Applicant returned to address corrections 7/12/2023 DANIEL SANJUAN
Plan Check Approved 8/3/2023 MICHAEL LOPEZ
Issued 8/11/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/23/2023 CELINA MORENO
Sewer availability Cleared 5/23/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/25/2023 CELINA MORENO
Historic Resource Verification Cleared 5/30/2023 MAX LODER
Tenant Habitability Plan Cleared 6/28/2023 ISMAEL HERNANDEZ
Community Plan Implem. Overlay Cleared 7/5/2023 RAFAEL FONTES
Redevelopment Project Area Cleared 7/6/2023 SUSAN WONG

Contact Information

Contractor Samama Albert; Lic. No.: 557517-B       ,
Contractor Socal Quake; Lic. No.: 557517-B       ,
Engineer Samama,, Albert; Lic. No.: C43288 22487 LIBERTY BELL RD      CALABASAS, CA 91302

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/6/2023 Approved ALFREDO LOPEZ
Pre-Inspection 9/20/2023 Corrections Issued RAMAZANALI ALMASI
Pre-Inspection 3/5/2024 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Not Ready JEROME BLACKWOOD
Interior/Exterior Lathing 4/26/2024 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 4/26/2024 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 2/24/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 7/1/2025 Approved JEROME BLACKWOOD
Insulation 7/11/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/17/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Drywall Nailing 7/25/2025 Approved JEROME BLACKWOOD
Final 2/13/2026 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 2/13/2026 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/13/2026 Conditional Approval DARRYL ARNOLD
Final 4/15/2026 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 4/15/2026 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/15/2026 Approved DARRYL ARNOLD
Final 6/15/2026 Not Ready for Inspection JEROME BLACKWOOD