6249-6249 1/2 E MERIDIAN ST 90042

Certificate Information: 6249-6249 1/2 E MERIDIAN ST 90042

Application / Permit
23016-10000-14107
Plan Check / Job No.
B23LA08205
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GROUND LEVEL GARAGE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 6/6/2023
Issuing Office
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/9/2023 LAWRENCE QUIRANTE
Corrections Issued 5/11/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 5/11/2023 APPLICANT
Plan Check Approved 6/2/2023 LUKE GONZALES
Issued 6/6/2023 APPLICANT
CofO in Progress 2/1/2024 ROY SPAULDING
Permit Finaled 2/14/2024 DEROLD HAUFF
CofO Issued 2/14/2024 DEROLD HAUFF
Permit Finaled 2/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/16/2023 BRIAN MILLER
Address approval Cleared 5/31/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2023 HUGO LOPEZ
Sewer availability Cleared 5/31/2023 HUGO LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/7/2023 Corrections Issued AMY COLIN
Insulation 8/7/2023 Not Ready for Inspection AMY COLIN
Wood Frame 8/7/2023 Not Ready for Inspection AMY COLIN
Deputy Drilled-In Anchors 8/9/2023 Conditional Approval AMY COLIN
Footing/Foundation/Slab 8/14/2023 Approved AMY COLIN
Insulation 8/14/2023 Approved AMY COLIN
PLUMBING-Rough 8/18/2023 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 8/23/2023 No Access for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 8/23/2023 No Access for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/28/2023 Approved AMY COLIN
PLUMBING-Rough 8/28/2023 Approved AMY COLIN
ELECTRICAL-Rough 10/2/2023 Approved ROY SPAULDING
Gas Test 10/2/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 10/2/2023 Approved ROY SPAULDING
PLUMBING-Rough 10/2/2023 Partial Approval ROY SPAULDING
Wood Frame 10/2/2023 Not Ready for Inspection ROY SPAULDING
HVAC-Rough 10/11/2023 Approved ROY SPAULDING
Wood Frame 10/11/2023 Approved ROY SPAULDING
Drywall Nailing 10/16/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 10/16/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 10/30/2023 Approved JOSH MEISTER
Shower Pan 10/30/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 1/9/2024 Approved ROY SPAULDING
Final 1/9/2024 Not Ready for Inspection ROY SPAULDING
Green Building Final 1/9/2024 Corrections Issued ROY SPAULDING
Green Building Rough 1/9/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 1/9/2024 Approved ROY SPAULDING
Final 1/12/2024 Corrections Issued ROY SPAULDING
Green Building Final 1/12/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved ROY SPAULDING
Final 1/22/2024 Corrections Issued ROY SPAULDING
Final 1/31/2024 OK to Issue CofO ROY SPAULDING