555 S FLOWER ST 25th Fl 90071

Certificate Information: 555 S FLOWER ST 25th Fl 90071

Application / Permit
23016-10000-14061
Plan Check / Job No.
B23LA08191
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan Office T.I. including new partitions, ceiling, finishes, and millwork.
Permit Issued
Issued on 10/24/2023
Issuing Office
Current Status
Permit Finaled on 5/28/2025

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/8/2023 PINANK PATEL
Corrections Issued 5/8/2023 PINANK PATEL
Plan Check Approved 10/12/2023 KEVIN MORALES
Issued 10/24/2023 APPLICANT
Permit Finaled 5/28/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 10/10/2023 DOMINIQUE MEDINA

Contact Information

Contractor Howard Building Corporation; Lic. No.: 445804-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2024 Partial Inspection JEROME BLACKWOOD
Green Building Rough 3/4/2024 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 3/4/2024 Partial Approval RAMAZANALI ALMASI
Insulation 3/6/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 3/11/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 3/11/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/13/2024 Partial Approval LUIS CCAMACHO
Insulation 3/13/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/19/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/26/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/11/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/23/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 5/7/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 5/7/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 6/3/2024 Not Ready for Inspection LUIS CCAMACHO
Structural Steel Frame 6/3/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 6/13/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 6/17/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/1/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 7/1/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 7/9/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/18/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/23/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/25/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 8/15/2024 Partial Approval JACOB MYERS
Light Gage Steel Frame 8/21/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 8/27/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 8/28/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 8/30/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 9/18/2024 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 9/18/2024 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 9/30/2024 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 10/9/2024 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 10/17/2024 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 10/17/2024 Partial Approval PAUL BAZERKANIAN
Special/Order Compliance 10/29/2024 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 10/29/2024 Partial Approval PAUL BAZERKANIAN
Final 5/28/2025 Permit Finaled PAUL BAZERKANIAN
Green Building Final 5/28/2025 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 5/28/2025 Approved PAUL BAZERKANIAN