5726 W 74TH ST 90045
Certificate Information: 5726 W 74TH ST 90045
- Application / Permit
- 23016-10000-14041
- Plan Check / Job No.
- B23LA08186
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing garage to ADU per state law, all work per WFPP
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2023 | MINA HABILI |
| Corrections Issued | 5/10/2023 | MINA HABILI |
| Applicant returned to address corrections | 4/10/2024 | KHUONG TRUONG |
| Plan Check Approved | 5/9/2024 | KHUONG TRUONG |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 2/26/2025 | BOBBY KEY |
| Permit Finaled | 2/27/2025 | RICHARD STEINBACH |
| CofO Issued | 2/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2023 | STEVEN JIN |
| Sewer availability | Cleared | 9/10/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 2/27/2024 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2024 | ANDREA SAINT-ANTONIN |
| Grading Pre-Inspection | Cleared | 5/1/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/11/2024 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 9/12/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/30/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Approved | BOBBY KEY |
| Green Building Rough | 9/30/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/30/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 9/30/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | JESUS PINEDA |
| Wood Frame | 10/8/2024 | Not Ready for Inspection | JESUS PINEDA |
| Underground Mechanical | 10/9/2024 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 10/10/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/15/2024 | Approved | BOBBY KEY |
| Green Building Rough | 10/15/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 10/15/2024 | Approved | BOBBY KEY |
| MERV13>=Rough | 10/15/2024 | Approved | BOBBY KEY |
| Gas Test | 10/18/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/18/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/22/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/22/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/7/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/21/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 2/21/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/21/2025 | Approved | TEMISTOCLES CAAL |
| MERV13>=Final | 2/21/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/21/2025 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 2/21/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/26/2025 | Approved | BOBBY KEY |
| Final | 2/26/2025 | OK to Issue CofO | BOBBY KEY |
| Gas Test | 2/26/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/26/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 2/26/2025 | Approved | BOBBY KEY |