4516 N LENNOX AVE 91423
Certificate Information: 4516 N LENNOX AVE 91423
- Application / Permit
- 23016-10000-13990
- Plan Check / Job No.
- B23LA08147
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage into 2 bedrooms and bathroom. No replacement parking required per AB 2097. All work per architect.
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 12/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2023 | KHUONG TRUONG |
| Corrections Issued | 5/9/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 5/17/2023 | VICTOR CHEN |
| Plan Check Approved | 6/13/2023 | AUNG SOE |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 11/8/2023 | MISAEL ESPARZA |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
| CofO Issued | 12/8/2023 | RUBEN SALAS |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/12/2023 | MEGAN GODINEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Eden Builders; Lic. No.: 891510-B | , |
| Contractor | Litman Inc; Lic. No.: 891510-B | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/3/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/3/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/8/2023 | Conditional Approval | MISAEL ESPARZA |
| Underground Mechanical | 8/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/23/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/23/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 8/23/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/23/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 8/31/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/7/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/7/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 9/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/11/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 9/11/2023 | Approved | MISAEL ESPARZA |
| Insulation | 9/18/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/18/2023 | Partial Approval | MISAEL ESPARZA |
| Insulation | 9/21/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/21/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/29/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | MISAEL ESPARZA |
| Final | 10/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/31/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 10/31/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/31/2023 | Approved | MISAEL ESPARZA |
| Final | 11/7/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 11/7/2023 | Approved | MISAEL ESPARZA |