4910-4912 N ALONZO AVE 91316

Certificate Information: 4910-4912 N ALONZO AVE 91316

Application / Permit
23016-10000-13888
Plan Check / Job No.
B23LA08068
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/4/2024
Issuing Office
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 DANIEL SMILEY
Corrections Issued 5/5/2023 DANIEL SMILEY
Applicant returned to address corrections 6/12/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/21/2023 MICHAEL LOPEZ
Applicant returned to address corrections 10/3/2023 MICHAEL LOPEZ
Applicant returned to address corrections 4/17/2024 LUKE GONZALES
Plan Check Approved 4/24/2024 LUKE GONZALES
Issued 5/4/2024 APPLICANT
CofO in Progress 10/10/2025 JOHN KIDWELL
Permit Finaled 1/5/2026 JOHN JANSON
CofO Issued 1/5/2026 JOHN JANSON
Permit Finaled 1/5/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/14/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 6/14/2023 FERNANDO GIL
Grading Pre-Inspection Cleared 6/14/2023 BRIAN MILLER
Sewer availability Cleared 6/14/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/6/2024 Approved JOHN KIDWELL
Underground Mechanical 8/6/2024 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/13/2024 Corrections Issued JOHN KIDWELL
Deputy Drilled-In Anchors 8/15/2024 Approved JOHN KIDWELL
Footing/Foundation/Slab 8/15/2024 Approved JOHN KIDWELL
Gas Test 8/15/2024 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 8/20/2024 Partial Approval JOHN KIDWELL
Gas Test 8/20/2024 Partial Approval JOHN KIDWELL
Green Building Rough 8/20/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 9/18/2024 Partial Approval SCOTT SOBEL
Gas Test 10/3/2024 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 10/3/2024 Approved JOHN KIDWELL
Shower Pan 10/3/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 11/26/2024 Corrections Issued JOHN COLEMAN
Drywall Nailing 11/26/2024 Corrections Issued JOHN COLEMAN
HVAC-Rough 11/26/2024 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 11/26/2024 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 9/4/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 9/4/2025 Approved JOHN KIDWELL
Final 9/4/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 9/4/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 9/4/2025 Approved JOHN KIDWELL
HVAC-Final 9/4/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 9/4/2025 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved JOHN KIDWELL
Smoke Detectors 9/4/2025 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 9/24/2025 Approved JOHN KIDWELL
Final 9/24/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 9/24/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 9/24/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 9/24/2025 Approved JOHN KIDWELL
Smoke Detectors 9/24/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 10/6/2025 Approved JOHN KIDWELL
Final 10/6/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 10/6/2025 Approved JOHN KIDWELL
HVAC-Final 10/6/2025 Approved JOHN KIDWELL
Final 10/9/2025 OK to Issue CofO JOHN KIDWELL