2010 1/4-1/2 S VINEYARD AVE 90016
Certificate Information: 2010 1/4-1/2 S VINEYARD AVE 90016
- Application / Permit
- 23016-10000-13831
- Plan Check / Job No.
- B23LA08040
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 118.45 SF ADDITION TO FIRST FLOOR GARAGE AND CONVERT (E) ATTACHED 2 CAR GARAGE BELOW (E) SFD TO ACCESSORY DWELLING (549.58 S.F) UNIT PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2023 | OMAR GARNICA |
| Corrections Issued | 5/10/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 5/23/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 5/26/2023 | MIROOSH KHACHATOORIAN |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 4/8/2024 | JUSTIN HAWLEY |
| CofO Issued | 4/10/2024 | DEROLD HAUFF |
| Permit Finaled | 4/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/11/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/17/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Corrections Issued | CALEB MEISTER |
| Underground Mechanical | 6/28/2023 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 6/29/2023 | Approved | CALEB MEISTER |
| Deputy Drilled-In Anchors | 6/30/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Other (see comments) | 6/30/2023 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 9/14/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 9/14/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 9/14/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/22/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 9/22/2023 | Approved | CALEB MEISTER |
| Insulation | 10/2/2023 | Approved | JOSH MEISTER |
| Deputy Wood Construction | 10/6/2023 | Conditional Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 10/17/2023 | Partial Approval | STUART CHAPMAN |
| Special/Order Compliance | 10/19/2023 | Corrections Issued | CALEB MEISTER |
| Verify Sprinkler Sign Off | 10/19/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/14/2023 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 11/14/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 11/14/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 11/14/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/20/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/20/2023 | Approved | STUART CHAPMAN |
| Gas Test | 1/19/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 3/1/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 3/1/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 3/1/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Not Required | JUSTIN HAWLEY |
| Service/Power Release | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 3/14/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/14/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Final | 3/14/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/14/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/14/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/14/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 3/15/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 3/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 4/8/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 4/8/2024 | Approved | JUSTIN HAWLEY |