1139 W BELLEVUE AVE Unit 6 90012
Certificate Information: 1139 W BELLEVUE AVE Unit 6 90012
- Application / Permit
- 23016-10000-13623
- Plan Check / Job No.
- B23LA07959
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING COVER PARKING 544 SF UNDER EXISTING APARTMENT BUILDING INTO ONE ADU per State Law, CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 10/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2023 | AUNG SOE |
| Corrections Issued | 5/12/2023 | AUNG SOE |
| Building Plans Picked Up | 5/18/2023 | APPLICANT |
| Applicant returned to address corrections | 7/7/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 7/10/2023 | WEIJIAN HUANG |
| Plan Check Approved | 9/11/2023 | MICHAEL LANZONE |
| Issued | 10/24/2023 | APPLICANT |
| CofO in Progress | 5/7/2024 | RAMAZANALI ALMASI |
| CofO Issued | 5/13/2024 | ERNESTO CORRAL |
| Permit Finaled | 5/13/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2023 | JEANIE LAM |
| Sewer availability | Cleared | 7/7/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/16/2023 | ROBERT HUGHES |
| Abandoned oil well | Cleared | 9/8/2023 | GILBERT URREA |
Contact Information
| Contractor | Courteous Construction Co Inc; Lic. No.: 567324-B | P O BOX 9287 GLENDALE, CA 91226 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/1/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 12/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | RAMAZANALI ALMASI |
| Green Building Rough | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 2/15/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 2/20/2024 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 2/20/2024 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 2/23/2024 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 2/29/2024 | Approved | RONALD JIMENEZ |
| Green Building Rough | 2/29/2024 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 2/29/2024 | Approved | RONALD JIMENEZ |
| Final | 5/1/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 5/1/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Final | 5/1/2024 | Approved | RAMAZANALI ALMASI |
| METHANE-Rough | 5/1/2024 | Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 5/1/2024 | Approved | RAMAZANALI ALMASI |
| Verify Rec and Parks Fee Memo | 5/1/2024 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 5/1/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 5/6/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Green Building Final | 5/6/2024 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 5/6/2024 | Approved | RAMAZANALI ALMASI |
| Final | 5/7/2024 | OK to Issue CofO | RAMAZANALI ALMASI |