4924 N GREENBUSH AVE 91423
Certificate Information: 4924 N GREENBUSH AVE 91423
- Application / Permit
- 23016-10000-13499
- Plan Check / Job No.
- B23LA07893
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Storage and Garage at Rear of The Lot Conversion to 32'-3" x 18'-3" detached Accessory Dwelling Unit Per GCS 65852.2(e)(1)(A) using Wood Frame Prescriptive Provisions (WFPP)
- Permit Issued
- Issued on 8/2/2023
- Issuing Office
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2023 | ALFRED RAMIREZ |
| Corrections Issued | 5/2/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/13/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/15/2023 | VICTOR CHEN |
| Plan Check Approved | 7/27/2023 | WEIJIAN HUANG |
| Issued | 8/2/2023 | APPLICANT |
| CofO in Progress | 8/5/2024 | MISAEL ESPARZA |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/3/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 9/8/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/8/2023 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/8/2023 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/8/2023 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/13/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 9/15/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 9/27/2023 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 9/27/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 9/27/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/28/2023 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/28/2023 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 9/28/2023 | No Access for Inspection | MISAEL ESPARZA |
| Underground Mechanical | 9/28/2023 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/5/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/5/2023 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 10/5/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Inspection | MISAEL ESPARZA |
| Wood Frame | 1/11/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/28/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/28/2024 | Approved | MISAEL ESPARZA |
| Insulation | 4/15/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 4/26/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 4/26/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/14/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/14/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/30/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 7/30/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 7/30/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 7/30/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | MISAEL ESPARZA |
| Final | 8/2/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 8/2/2024 | Approved | MISAEL ESPARZA |