1464 N LOGAN ST 1-4 90026
Certificate Information: 1464 N LOGAN ST 1-4 90026
- Application / Permit
- 23016-10000-13388
- Plan Check / Job No.
- B23LA07848
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan Interior remodel to (e) 2-story apartment. Work to include:CONVERT 3 UNIT APARTMENT TO 4 UNIT APARTMENT BY DIVIDING THE SECOND FLOOR UNIT TO TWO relocate kitchen and add an interior bedroom in all units , relocate bathrooms in upstair units , and replace water heaters with tankless water heaters in each unit
- Permit Issued
- Issued on 11/29/2023
- Issuing Office
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2023 | JASON JANGADA |
| Corrections Issued | 5/2/2023 | JASON JANGADA |
| Applicant returned to address corrections | 11/14/2023 | SHANGQIN XIE |
| Plan Check Approved | 11/21/2023 | ARSALAN SHABESTARI |
| Issued | 11/29/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | RONALD JIMENEZ |
| Permit Finaled | 10/3/2024 | RAFAEL ESPINOZA |
| CofO Issued | 10/3/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 10/3/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/30/2023 | DAVID LOPEZ |
| Tenant Habitability Plan | Cleared | 11/6/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Embark Adu; Lic. No.: 970997-B | , |
| Contractor | Esk Construction Inc; Lic. No.: 970997-B | , |
| Engineer | Braun,, Jason William; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
| Engineer | Braun,, Jason William; Lic. No.: NA70948 | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/14/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 3/12/2024 | Corrections Issued | RAMAZANALI ALMASI |
| Wood Frame | 3/27/2024 | Approved | RAMAZANALI ALMASI |
| Insulation | 4/2/2024 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 4/10/2024 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 4/10/2024 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 4/12/2024 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 4/18/2024 | Approved | RAMAZANALI ALMASI |
| Final | 10/2/2024 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 10/2/2024 | Approved | RONALD JIMENEZ |
| Final | 10/3/2024 | OK to Issue CofO | RONALD JIMENEZ |