8412 S ALVERSTONE AVE 90045
Certificate Information: 8412 S ALVERSTONE AVE 90045
- Application / Permit
- 23016-10000-13357
- Plan Check / Job No.
- B23LA07824
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1-STORY RECREATION ROOM TO ADU (351 SF) PER GCS 6585.2(E)(1)(A). NO STRUCTURAL WORK, NEW NON-BEARING WALLS PER WFPP. NO CHANGE IN BUILDING DIMENSIONS OR HEIGHT.
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | KHUONG TRUONG |
| Corrections Issued | 4/27/2023 | KHUONG TRUONG |
| Plan Check Approved | 5/23/2023 | DANIEL SMILEY |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 6/30/2023 | HERBERT GIRON |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/28/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 5/17/2023 | JOSHUA JONES |
Contact Information
| Contractor | Great American Garage Conversions; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2023 | Partial Inspection | HERBERT GIRON |
| Pre-Inspection | 6/6/2023 | Partial Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 6/8/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 6/8/2023 | Approved | HERBERT GIRON |
| Insulation | 6/8/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/8/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 6/8/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 6/13/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 6/13/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 6/14/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | HERBERT GIRON |
| Final | 6/27/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 6/27/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 6/27/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 6/27/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/30/2023 | Approved | HERBERT GIRON |
| Final | 6/30/2023 | OK to Issue CofO | HERBERT GIRON |