8412 S ALVERSTONE AVE 90045

Certificate Information: 8412 S ALVERSTONE AVE 90045

Application / Permit
23016-10000-13357
Plan Check / Job No.
B23LA07824
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 1-STORY RECREATION ROOM TO ADU (351 SF) PER GCS 6585.2(E)(1)(A). NO STRUCTURAL WORK, NEW NON-BEARING WALLS PER WFPP. NO CHANGE IN BUILDING DIMENSIONS OR HEIGHT.
Permit Issued
Issued on 5/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 KHUONG TRUONG
Corrections Issued 4/27/2023 KHUONG TRUONG
Plan Check Approved 5/23/2023 DANIEL SMILEY
Issued 5/23/2023 APPLICANT
CofO in Progress 6/30/2023 HERBERT GIRON
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/28/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/28/2023 ANTHONY MAINEZ
Sewer availability Cleared 4/28/2023 ANTHONY MAINEZ
Specific Plan Cleared 5/17/2023 JOSHUA JONES

Contact Information

Contractor Great American Garage Conversions; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2023 Partial Inspection HERBERT GIRON
Pre-Inspection 6/6/2023 Partial Inspection HERBERT GIRON
BUILDING-Rough-Frame 6/8/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 6/8/2023 Approved HERBERT GIRON
HVAC-Rough 6/8/2023 Approved HERBERT GIRON
Insulation 6/8/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 6/8/2023 Approved HERBERT GIRON
PLUMBING-Rough 6/8/2023 Approved HERBERT GIRON
Drywall Nailing 6/13/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 6/13/2023 Approved HERBERT GIRON
Drywall Nailing 6/14/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/27/2023 Corrections Issued HERBERT GIRON
Final 6/27/2023 Corrections Issued HERBERT GIRON
HVAC-Final 6/27/2023 Approved HERBERT GIRON
PLUMBING-Final 6/27/2023 Approved HERBERT GIRON
Smoke Detectors 6/27/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/30/2023 Approved HERBERT GIRON
Final 6/30/2023 OK to Issue CofO HERBERT GIRON
Green Building Final 6/30/2023 Approved HERBERT GIRON