900 N LA BREA AVE 5 90038
Certificate Information: 900 N LA BREA AVE 5 90038
- Application / Permit
- 23016-10000-13331
- Plan Check / Job No.
- B23LA07802
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- eplan. Change of use and tenant improvement of an existing 1,515 usf retail space into a new Dental Clinic, HOURS OF OPERATION FROM 7am TO 11pm.
- Permit Issued
- Issued on 7/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/4/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/8/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/12/2023 | MOHAMMAD ESMAILI |
| Issued | 7/15/2023 | APPLICANT |
| CofO in Progress | 4/2/2024 | ALFREDO LOPEZ |
| CofO in Progress | 4/2/2024 | RAFAEL ESPINOZA |
| CofO in Progress | 4/2/2024 | ALFREDO LOPEZ |
| Permit Finaled | 4/2/2024 | ERNESTO CORRAL |
| CofO Issued | 4/2/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 5/5/2023 | MAXFIELD VERMY |
| "Q" conditions | Cleared | 5/5/2023 | MAXFIELD VERMY |
| "T" removal | Cleared | 5/5/2023 | MAXFIELD VERMY |
| Comm Cor/Mini-Mall | Cleared | 5/5/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 5/5/2023 | MAXFIELD VERMY |
| ZI | Cleared | 5/5/2023 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2023 | KEVIN AVILA |
| Sewer availability | Cleared | 6/10/2023 | KEVIN AVILA |
Contact Information
| Contractor | Garrett Construction Inc; Lic. No.: 974349-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2023 | Conditional Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 9/11/2023 | Approved | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/15/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/16/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/17/2023 | Corrections Issued | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 11/20/2023 | Conditional Approval | RICARDO ROBLES |
| Insulation | 11/20/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/20/2023 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/21/2023 | Approved | RICARDO ROBLES |
| Drywall Nailing | 11/27/2023 | Approved | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/27/2023 | Partial Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 1/17/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 1/18/2024 | Conditional Approval | ALFREDO LOPEZ |
| Final | 2/16/2024 | Partial Approval | ALFREDO LOPEZ |
| METHANE-Final | 2/16/2024 | Approved | ALFREDO LOPEZ |
| METHANE-Rough | 2/16/2024 | Approved | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 2/16/2024 | Approved | ALFREDO LOPEZ |
| Reinforced Masonry Frame | 2/16/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 2/16/2024 | Approved | ALFREDO LOPEZ |
| Final | 4/2/2024 | OK to Issue CofO | ALFREDO LOPEZ |