900 N LA BREA AVE 5 90038

Certificate Information: 900 N LA BREA AVE 5 90038

Application / Permit
23016-10000-13331
Plan Check / Job No.
B23LA07802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Dental Clinic
Work Description
eplan. Change of use and tenant improvement of an existing 1,515 usf retail space into a new Dental Clinic, HOURS OF OPERATION FROM 7am TO 11pm.
Permit Issued
Issued on 7/15/2023
Issuing Office
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2023 APPLICANT
Assigned to Plan Check Engineer 5/3/2023 MOHAMMAD ESMAILI
Corrections Issued 5/4/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/8/2023 MOHAMMAD ESMAILI
Plan Check Approved 7/12/2023 MOHAMMAD ESMAILI
Issued 7/15/2023 APPLICANT
CofO in Progress 4/2/2024 ALFREDO LOPEZ
CofO in Progress 4/2/2024 RAFAEL ESPINOZA
CofO in Progress 4/2/2024 ALFREDO LOPEZ
Permit Finaled 4/2/2024 ERNESTO CORRAL
CofO Issued 4/2/2024 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 5/5/2023 MAXFIELD VERMY
"Q" conditions Cleared 5/5/2023 MAXFIELD VERMY
"T" removal Cleared 5/5/2023 MAXFIELD VERMY
Comm Cor/Mini-Mall Cleared 5/5/2023 MAXFIELD VERMY
ZA Case Cleared 5/5/2023 MAXFIELD VERMY
ZI Cleared 5/5/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 6/10/2023 KEVIN AVILA
Sewer availability Cleared 6/10/2023 KEVIN AVILA

Contact Information

Contractor Garrett Construction Inc; Lic. No.: 974349-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/6/2023 Conditional Approval ALFREDO LOPEZ
Footing/Foundation/Slab 9/11/2023 Approved ALFREDO LOPEZ
Light Gage Steel Frame 11/15/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 11/16/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 11/17/2023 Corrections Issued RICARDO ROBLES
Deputy Drilled-In Anchors 11/20/2023 Conditional Approval RICARDO ROBLES
Insulation 11/20/2023 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 11/20/2023 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 11/21/2023 Approved RICARDO ROBLES
Drywall Nailing 11/27/2023 Approved ALFREDO LOPEZ
Light Gage Steel Frame 11/27/2023 Partial Approval ALFREDO LOPEZ
T-Bar Ceiling 1/17/2024 Not Ready for Inspection ALFREDO LOPEZ
T-Bar Ceiling 1/18/2024 Conditional Approval ALFREDO LOPEZ
Final 2/16/2024 Partial Approval ALFREDO LOPEZ
METHANE-Final 2/16/2024 Approved ALFREDO LOPEZ
METHANE-Rough 2/16/2024 Approved ALFREDO LOPEZ
Reinforced Concrete Frame 2/16/2024 Approved ALFREDO LOPEZ
Reinforced Masonry Frame 2/16/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 2/16/2024 Approved ALFREDO LOPEZ
Final 4/2/2024 OK to Issue CofO ALFREDO LOPEZ