1700 N AVENUE 53 90042

Certificate Information: 1700 N AVENUE 53 90042

Application / Permit
23016-10000-13329
Plan Check / Job No.
B23LA07800
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: INTERIOR AND EXTERIOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/14/2023
Issuing Office
Current Status
CofO Issued on 12/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2023 APPLICANT
Assigned to Plan Check Engineer 5/2/2023 MINA HABILI
Corrections Issued 5/3/2023 MINA HABILI
Applicant returned to address corrections 6/8/2023 MINA HABILI
Applicant returned to address corrections 6/28/2023 MINA HABILI
Applicant returned to address corrections 7/20/2023 MINA HABILI
Applicant returned to address corrections 7/28/2023 DANIEL YIP
Plan Check Approved 8/10/2023 DANIEL YIP
Issued 8/14/2023 APPLICANT
CofO in Progress 12/17/2024 ALIZAH MAYAGOITIA
Permit Finaled 12/20/2024 DEROLD HAUFF
CofO Issued 12/20/2024 DEROLD HAUFF
Permit Finaled 12/20/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/10/2023 SERGIO VALENZUELA
Tenant Habitability Plan Cleared 7/13/2023 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/1/2024 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/1/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/15/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 5/17/2024 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/23/2024 Approved CRAIG VAUGHAN
HVAC-Rough 5/23/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 5/23/2024 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 5/24/2024 Approved CRAIG VAUGHAN
Green Building Rough 5/24/2024 Approved CRAIG VAUGHAN
HVAC-Rough 5/24/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/24/2024 Approved CRAIG VAUGHAN
Wood Frame 5/24/2024 Approved CRAIG VAUGHAN
Insulation 5/31/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/31/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 6/6/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/6/2024 Approved CRAIG VAUGHAN
Underground Mechanical 10/9/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/12/2024 Corrections Issued ALIZAH MAYAGOITIA
Final 11/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 11/12/2024 Approved ALIZAH MAYAGOITIA
Gas Test 11/12/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 11/12/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 11/12/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 11/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 11/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 11/12/2024 Approved ALIZAH MAYAGOITIA
Service/Power Release 11/15/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/13/2024 Approved ROY SPAULDING
Final 12/13/2024 Not Ready for Inspection ROY SPAULDING
HVAC-Final 12/13/2024 Approved ROY SPAULDING
PLUMBING-Final 12/13/2024 Corrections Issued ROY SPAULDING
Final 12/16/2024 Conditional Approval BRENDAN MORELLI
Final 12/17/2024 OK to Issue CofO ALIZAH MAYAGOITIA