6031 E FAYETTE ST 90042

Certificate Information: 6031 E FAYETTE ST 90042

Application / Permit
23016-10000-13320
Plan Check / Job No.
B23LA07797
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) detached garage in to accessory dwelling unit (ADU) per state law
Permit Issued
Issued on 6/27/2023
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 5/1/2023 DANIEL SANJUAN
Corrections Issued 5/2/2023 DANIEL SANJUAN
Applicant returned to address corrections 5/12/2023 DANIEL YIP
Applicant returned to address corrections 5/23/2023 MINA HABILI
Applicant returned to address corrections 5/26/2023 MINA HABILI
Plan Check Approved 6/8/2023 MINA HABILI
Issued 6/27/2023 APPLICANT
CofO in Progress 11/3/2023 ROY SPAULDING
CofO Issued 11/8/2023 DEROLD HAUFF
Permit Finaled 11/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/5/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 5/5/2023 ALEXANDER HELFER
Sewer availability Cleared 5/5/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/11/2023 TREVOR QUAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Your Favorite Contractor Inc; Lic. No.: 851344-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/3/2023 Conditional Approval CRAIG VAUGHAN
Underground Mechanical 8/4/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/8/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/1/2023 Approved CRAIG VAUGHAN
Shower Pan 9/1/2023 Approved CRAIG VAUGHAN
Insulation 9/8/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/8/2023 Partial Approval CRAIG VAUGHAN
Drywall Nailing 9/13/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/13/2023 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/25/2023 Partial Approval ROY SPAULDING
Final 10/25/2023 Corrections Issued ROY SPAULDING
Green Building Final 10/25/2023 Not Ready for Inspection ROY SPAULDING
Green Building Rough 10/25/2023 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved ROY SPAULDING
Smoke Detectors 10/25/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/2/2023 Approved ROY SPAULDING
Final 11/2/2023 OK to Issue CofO ROY SPAULDING
Green Building Final 11/2/2023 Approved ROY SPAULDING
Green Building Rough 11/2/2023 Approved ROY SPAULDING