626 1/2-1/4 W 80TH ST 90044
Certificate Information: 626 1/2-1/4 W 80TH ST 90044
- Application / Permit
- 23016-10000-13315
- Plan Check / Job No.
- B23LA07782
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE AT FIRST FLOOR INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) FOR EX. SFD. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/9/2025
- Issuing Office
- Current Status
- Issued on 5/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2023 | PINANK PATEL |
| Corrections Issued | 5/13/2023 | PINANK PATEL |
| Plan Check Approved | 1/5/2024 | ROSENDO MEDINA |
| Issued | 5/9/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 6/27/2023 | JESSICA OPINION |
| "Q" conditions | Cleared | 6/28/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 9/9/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Iah Construction Corp; Lic. No.: 1104704-B | , |
| Engineer | Park,, Juntae; Lic. No.: NA65104 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/22/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 5/27/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 8/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/25/2025 | Conditional Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Conditional Approval | JOHN QUINTANILLA |
| HVAC-Rough | 12/9/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/7/2026 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 1/7/2026 | Corrections Issued | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 1/7/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/9/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 1/9/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/16/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 1/16/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/16/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/30/2026 | No Access for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 2/3/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 2/25/2026 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 3/17/2026 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 3/25/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Shower Pan | 4/30/2026 | Approved | JOHN QUINTANILLA |