921 S BEACON ST STE A 90731

Certificate Information: 921 S BEACON ST STE A 90731

Application / Permit
23016-10000-13238
Plan Check / Job No.
B23LA07734
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
*eplan* T.I TO THE (E) FIRST FLOOR RESTAURANT AND PATIO. (NO LANDSCAPE WORK OR POOL WORK TO BE COMPLETED UNDER THIS PERMIT.)
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
Permit Finaled on 10/20/2025

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 GARO TELMI
Corrections Issued 5/13/2023 GARO TELMI
Quality Review Completed 5/25/2023 CHARLES CHANG
Applicant returned to address corrections 4/5/2024 GARO TELMI
Applicant returned to address corrections 4/16/2024 GARO TELMI
Plan Check Approved 5/3/2024 GARO TELMI
Issued 5/3/2024 APPLICANT
Permit Finaled-Status Void 8/14/2024 JOEY BUCHANAN
Re-Activate Permit 11/6/2024 JOEY BUCHANAN
Permit Finaled 10/20/2025 MICHAEL PETRUSKO

Permit Application Clearance Information

HPOZ Cleared 5/15/2023 LAMBERT GIESSINGER
Historic Resource Verification Cleared 5/15/2023 LAMBERT GIESSINGER
Miscellaneous Cleared 5/16/2023 JAZMIN ROQUE
Redevelopment Project Area Cleared 5/17/2023 SUSAN WONG
Fire Marshal Fire Life Safety Cleared 6/16/2023 MENOA AGHAJANI
Eng Process Fee Ord 176,300 Cleared 7/10/2023 ANA SORIANO
DAS Clearance Cleared 12/18/2023 Lawrence Quirante
Green Code Cleared 2/22/2024 AARON COSTA
Food Service Establishment Cleared 4/16/2024 PAWAN VERMA
Food establishment approval Cleared 5/3/2024 LACDHS APPROVED

Contact Information

Architect Liljegren,, Karin J; Lic. No.: C28158 600 CRANE BLVD      LOS ANGELES, CA 90065
Contractor M D M Builders Group; Lic. No.: 933238-B       ,
Contractor M Librush Construction Inc; Lic. No.: 933238-B       ,

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 8/14/2024 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 8/14/2024 Approved JOEY BUCHANAN
Green Building Rough 8/14/2024 Approved JOEY BUCHANAN
Reinforced Concrete Frame 8/14/2024 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 8/14/2024 Approved JOEY BUCHANAN
Light Gage Steel Frame 1/10/2025 Approved MICHAEL PETRUSKO
Insulation 2/11/2025 Approved MICHAEL PETRUSKO
Light Gage Steel Frame 2/11/2025 Approved MICHAEL PETRUSKO
Drywall Nailing 3/3/2025 Approved JOEY BUCHANAN
Drywall Nailing 3/12/2025 Approved MICHAEL PETRUSKO
Special/Order Compliance 5/14/2025 Approved JOEY BUCHANAN
Special/Order Compliance 6/3/2025 Conditional Approval MICHAEL PETRUSKO
Final 9/17/2025 Partial Approval DAVID TSAU
Final 10/8/2025 Corrections Issued MICHAEL PETRUSKO
Final 10/20/2025 Permit Finaled MICHAEL PETRUSKO