1000 E INDIANA AVE 90291

Certificate Information: 1000 E INDIANA AVE 90291

Application / Permit
23016-10000-13221
Plan Check / Job No.
B23LA07723
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPlan: Interior Remodel for Bathroom and Kitchen in (E) 1-Story SFD, NO CHANGE OF SQUARE FOOTAGE. NO CHANGE OF USE.
Permit Issued
Issued on 6/2/2023
Issuing Office
Current Status
Permit Finaled on 4/5/2024

Permit Application Status History

Submitted 5/1/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 DAVID CASTILLO
Corrections Issued 5/5/2023 DAVID CASTILLO
Applicant returned to address corrections 5/31/2023 JOHNPAUL ISIP
Plan Check Approved 6/1/2023 JASON JANGADA
Issued 6/2/2023 APPLICANT
Permit Finaled 4/5/2024 HERBERT GIRON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/23/2023 DARIN LAM
Roof/Waste drainage to street Cleared 5/23/2023 DARIN LAM

Contact Information

Architect Duran,, Alfonso; Lic. No.: NA40148       ,
Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: NA78115       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 9/20/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 9/22/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 9/22/2023 Approved HERBERT GIRON
Gas Test 9/22/2023 Approved HERBERT GIRON
HVAC-Rough 9/22/2023 Approved HERBERT GIRON
PLUMBING-Rough 9/22/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/29/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 9/29/2023 Partial Approval HERBERT GIRON
Shower Pan 9/29/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/4/2023 Approved HERBERT GIRON
Green Building Rough 10/4/2023 Approved HERBERT GIRON
Insulation 10/4/2023 Approved HERBERT GIRON
Drywall Nailing 10/17/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 10/25/2023 Approved HERBERT GIRON
Gas Test 2/28/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 2/28/2024 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 3/1/2024 Approved HERBERT GIRON
HVAC-Final 3/1/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/1/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 4/2/2024 Approved HERBERT GIRON
Final 4/2/2024 Corrections Issued HERBERT GIRON
HVAC-Final 4/2/2024 Approved HERBERT GIRON
PLUMBING-Final 4/2/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 4/2/2024 Approved HERBERT GIRON
Final 4/5/2024 Permit Finaled HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved HERBERT GIRON