1822 S MANSFIELD AVE 90019
Certificate Information: 1822 S MANSFIELD AVE 90019
- Application / Permit
- 23016-10000-13004
- Plan Check / Job No.
- B23LA07615
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/exterior remodel of an existing single-family dwelling. All work done per engineered design.
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/15/2023
Permit Application Status History
| Submitted | 4/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2023 | RAHEL BEYENE |
| Corrections Issued | 4/25/2023 | RAHEL BEYENE |
| Plan Check Approved | 5/15/2023 | DANIEL SMILEY |
| Issued | 5/15/2023 | APPLICANT |
| Permit Finaled | 9/14/2023 | LILIANA PORTILLO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Vanessa, Jauregui; Lic. No.: C38627 | 4510 10TH AVE LOS ANGELES, CA 90043 |
| Contractor | Owner-Builder | , |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/26/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/30/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/16/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 6/26/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/26/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 6/26/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/26/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/3/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 7/3/2023 | Approved | JOSE AVILA |
| Insulation | 7/3/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 7/5/2023 | Conditional Approval | JOSE AVILA |
| Drywall Nailing | 7/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/8/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/8/2023 | Approved | LILIANA PORTILLO |
| Final | 8/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 8/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/8/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 9/8/2023 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 9/8/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/14/2023 | Approved | LILIANA PORTILLO |
| Final | 9/14/2023 | Permit Finaled | LILIANA PORTILLO |
| HVAC-Final | 9/14/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 9/14/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | LILIANA PORTILLO |