1422 N TAMARIND AVE 1-19 90028
Certificate Information: 1422 N TAMARIND AVE 1-19 90028
- Application / Permit
- 23016-10000-13000
- Plan Check / Job No.
- B23LA07612
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert existing 2 parking stalls in the garage and storage room to 2 ADUs. Convert existing laundry room and encloseportion of the garage area to a new recreation room. Enclose a portion of the garage area to a enlarge the storage room
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2023 | MADISON ODELL |
| Corrections Issued | 5/2/2023 | MADISON ODELL |
| Applicant returned to address corrections | 12/13/2023 | MADISON ODELL |
| Plan Check Approved | 9/11/2024 | SAM CHANG |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 4/2/2026 | DAVID BURKHEAD |
| Permit Finaled | 4/2/2026 | ERNESTO CORRAL |
| CofO Issued | 4/2/2026 | ERNESTO CORRAL |
| Permit Finaled | 4/2/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2023 | MSTAFA AL-MSARI |
| "Q" conditions | Cleared | 9/30/2023 | RYAN LY |
| ZI | Cleared | 9/30/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 10/12/2023 | JESSICA OPINION |
| Redevelopment Project Area | Cleared | 10/16/2023 | DAVID URITA |
| Fire Marshal Fire Life Safety | Cleared | 6/18/2024 | DOMINIQUE MEDINA |
| Green Code | Cleared | 7/3/2024 | MICHAEL MARTINEZ |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: C30005 | 10999 RIVERSIDE DRIVE SUITE 300 STUDIO CITY, CA 91602 |
| Contractor | Stc Builders Inc; Lic. No.: 1101356-B | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2025 | Approved | TIMOTHY POWELL |
| Pre-Inspection | 3/25/2025 | Approved | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/14/2025 | Partial Approval | LUIS CCAMACHO |
| Reinforced Concrete Frame | 5/14/2025 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 5/23/2025 | Partial Inspection | TIMOTHY POWELL |
| Reinforced Concrete Frame | 5/23/2025 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/29/2025 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 6/18/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 6/18/2025 | Partial Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 8/22/2025 | Approved | LUIS CCAMACHO |
| Wood Frame | 8/22/2025 | Partial Approval | LUIS CCAMACHO |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 9/11/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 9/11/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Not Ready | LUIS CCAMACHO |
| Smoke Detectors | 9/11/2025 | No Access for Inspection | LUIS CCAMACHO |
| Wood Frame | 9/11/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Wood Frame | 9/16/2025 | Partial Approval | TIMOTHY POWELL |
| Insulation | 9/24/2025 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 9/26/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 10/1/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 10/21/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Order to Comply | 12/10/2025 | Not Required | LARRY ARNICK |
| Final | 3/5/2026 | Partial Inspection | LUIS CCAMACHO |
| Green Building Final | 3/5/2026 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 3/5/2026 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 3/5/2026 | Approved | LUIS CCAMACHO |
| Wood Frame | 3/5/2026 | Approved | LUIS CCAMACHO |
| Final | 3/17/2026 | Partial Inspection | DAVID BURKHEAD |
| Final | 4/2/2026 | OK to Issue CofO | DAVID BURKHEAD |