5681 W HILL OAK DR 90068

Certificate Information: 5681 W HILL OAK DR 90068

Application / Permit
23016-10000-12801
Plan Check / Job No.
B23LA07533
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONVERT (E) STORAGE (78SQFT)+ATTACHED GARAGE (444SQFT) TO ADU (518SQFT) PER STATE LAW
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 KHUONG TRUONG
Corrections Issued 4/28/2023 KHUONG TRUONG
Plan Check Approved 6/26/2023 KHUONG TRUONG
Issued 7/7/2023 APPLICANT
CofO in Progress 2/8/2024 BRIAN SULLIVAN
Permit Finaled 4/1/2024 RONALD MYRICK
CofO Issued 4/1/2024 RONALD MYRICK
Permit Finaled 4/1/2024 RONALD MYRICK

Permit Application Clearance Information

"D" conditions Cleared 5/3/2023 JASON CHAN
Address approval Cleared 5/3/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/3/2023 JEANIE LAM
Sewer availability Cleared 5/3/2023 JEANIE LAM
ZI Cleared 5/3/2023 JASON CHAN
Grading Pre-Inspection Cleared 6/26/2023 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 7/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 7/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 7/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 7/12/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/17/2023 Approved STUART CHAPMAN
HVAC-Rough 7/17/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/17/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/1/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 8/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 8/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 8/17/2023 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 8/22/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 8/22/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/25/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/25/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 9/25/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 9/25/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 9/25/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/2/2023 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 10/2/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 10/2/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 10/3/2023 Corrections Issued JOAQUIN GREENOUGH
Insulation 10/4/2023 Partial Approval STUART CHAPMAN
Sewer 10/4/2023 Not Ready for Inspection STUART CHAPMAN
Sewer 10/12/2023 Approved JOAQUIN GREENOUGH
Underground Mechanical 10/12/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 10/19/2023 Approved BRENDAN MORELLI
Shower Pan 10/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/27/2023 No Access for Inspection RAUL BARAJAS
ELECTRICAL-Rough 10/31/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/31/2023 Corrections Issued JOAQUIN GREENOUGH
Shower Pan 10/31/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/2/2023 Approved JOAQUIN GREENOUGH
Pre-Inspection 11/17/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 12/20/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/26/2024 Approved ROY SPAULDING
Final 1/26/2024 Corrections Issued ROY SPAULDING
Green Building Final 1/26/2024 Approved ROY SPAULDING
Green Building Rough 1/26/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 1/26/2024 Approved ROY SPAULDING
Final 2/7/2024 OK to Issue CofO BRIAN SULLIVAN