1749 N AVENUE 53 90042
Certificate Information: 1749 N AVENUE 53 90042
- Application / Permit
- 23016-10000-12786
- Plan Check / Job No.
- B23LA07516
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR REMODEL THROUGH OUT (E) SFD. ALL WORK PER ENG.
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/21/2025
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/28/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/15/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/12/2023 | LUISANGEL VALENZUELA |
| Issued | 1/11/2024 | APPLICANT |
| Permit Finaled | 3/20/2025 | DAVID WILLIAMS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/29/2023 | ROBERT HUGHES |
Contact Information
| Architect | Masterman,, Susan L; Lic. No.: NA26870 | , |
| Contractor | Veba Builders Inc; Lic. No.: 1047822-B | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: NA43720 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 4/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Gas Test | 5/3/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 5/3/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 5/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 5/6/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/6/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 5/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 5/9/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 5/14/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/14/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/23/2024 | Approved | BRENDAN MORELLI |
| Final | 3/20/2025 | Permit Finaled | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 3/20/2025 | Approved | DAVID WILLIAMS |