1243 1/2 S POINT VIEW ST 90035
Certificate Information: 1243 1/2 S POINT VIEW ST 90035
- Application / Permit
- 23016-10000-12753
- Plan Check / Job No.
- B23LA07505
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan Convert Existing Detached Garage into ADU per state law. All work done per engineered design. ***see comments
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | JOSEPH RAFOLS |
| Corrections Issued | 5/1/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 7/27/2023 | MINA HABILI |
| Applicant returned to address corrections | 8/2/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 8/24/2023 | DANIEL SMILEY |
| Plan Check Approved | 9/2/2023 | AUNG SOE |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 1/6/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/11/2023 | JEANIE LAM |
| City Hist. Cultural Monument | Cleared | 8/2/2023 | JONATHAN KAPLAN |
| HPOZ | Cleared | 8/2/2023 | JONATHAN KAPLAN |
| Construction within easement | Cleared | 8/22/2023 | TINA MIRANDA |
Contact Information
| Contractor | Saan Construction Inc; Lic. No.: 818322-B | 2837 EL CAMINITO STREET LA CRESCENTA, CA 91214 |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/28/2024 | Partial Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 4/8/2024 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/20/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/20/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 5/20/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 5/20/2024 | Approved | ARTHUR NEGRETE |
| Wood Frame | 5/20/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 5/29/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/29/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 5/29/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 6/4/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/4/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/25/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Not Ready | JOSE MACIAS |
| ELECTRICAL-Final | 10/28/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 10/28/2024 | Approved | ARTHUR NEGRETE |
| Light Gage Steel Frame | 10/28/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 10/28/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 10/28/2024 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 10/28/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | ARTHUR NEGRETE |
| Final | 11/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 11/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 11/18/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Final | 11/18/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 11/18/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 11/18/2024 | Approved | ARTHUR NEGRETE |
| Final | 12/12/2024 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 12/12/2024 | Approved | ARTHUR NEGRETE |
| Final | 12/17/2024 | Conditional Approval | ARTHUR NEGRETE |
| Final | 1/6/2026 | OK to Issue CofO | BRENDAN MORELLI |