3539 1/2 E 8TH ST 90023

Certificate Information: 3539 1/2 E 8TH ST 90023

Application / Permit
23016-10000-12621
Plan Check / Job No.
B23LA07466
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/28/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 ALEC MOUSAKHANIAN
Corrections Issued 5/5/2023 ALEC MOUSAKHANIAN
Plan Check Approved 8/26/2023 ALEC MOUSAKHANIAN
Issued 8/28/2023 APPLICANT
CofO in Progress 1/3/2024 ALIZAH MAYAGOITIA
No Progress 1/8/2024 SCOTT FINNILA
CofO in Progress 1/10/2024 DEROLD HAUFF
CofO Issued 1/10/2024 DEROLD HAUFF
Permit Finaled 1/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/14/2023 RIDWAN HARDY
Construction within easement Cleared 8/14/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/22/2023 AMBER CAMPBELL
Address approval Cleared 8/23/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 8/23/2023 AMBER CAMPBELL
Sewer availability Cleared 8/23/2023 AMBER CAMPBELL
ZI Cleared 8/25/2023 DAVID URITA
ZI Cleared 8/25/2023 DAVID URITA

Contact Information

Contractor Owner-Builder       ,
Engineer Abarquez,, Jose Munoz; Lic. No.: C51994 18 EL CORZO      RANCHO SANTA MARGARITA, CA 92688

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/25/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 9/25/2023 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 10/11/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 10/11/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 10/11/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 10/11/2023 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/17/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/20/2023 Approved FREDDIE RIVERA
ELECTRICAL-Rough 10/20/2023 Approved FREDDIE RIVERA
Green Building Rough 10/20/2023 Approved FREDDIE RIVERA
HVAC-Rough 10/20/2023 Approved FREDDIE RIVERA
Insulation 10/24/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/24/2023 Conditional Approval FREDDIE RIVERA
Drywall Nailing 10/27/2023 Approved FREDDIE RIVERA
Final 12/4/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Final 12/4/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 12/4/2023 Approved FREDDIE RIVERA
Final 12/19/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready ENRIQUE MIRELES
Final 12/27/2023 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/27/2023 SGSOV Approved ALIZAH MAYAGOITIA
Final 1/2/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 1/2/2024 Approved ALIZAH MAYAGOITIA