5457 N WILLIS AVE 91411

Certificate Information: 5457 N WILLIS AVE 91411

Application / Permit
23016-10000-11878
Plan Check / Job No.
B23LA07012
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition for new 27 sq. ft. living room extension and re-roof frame of the (E) house to have higher ceilings
Permit Issued
Issued on 11/1/2023
Issuing Office
Current Status
Issued on 11/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 4/21/2023 KHUONG TRUONG
Corrections Issued 4/22/2023 KHUONG TRUONG
Applicant returned to address corrections 9/7/2023 KHUONG TRUONG
Applicant returned to address corrections 9/22/2023 KHUONG TRUONG
Applicant returned to address corrections 10/7/2023 GEORGE ALVAREZ
Plan Check Approved 10/25/2023 JOE VO
Plan Check Approved 10/30/2023 JOE VO
Issued 11/1/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/22/2023 JEANIE LAM
Low Impact Development (LID) Cleared 8/23/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 8/29/2023 JOHN LIN

Contact Information

Contractor Precision Construction Experts Inc; Lic. No.: 1026997-B       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2024 No Access for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/11/2025 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 4/11/2025 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/17/2025 Not Ready for Inspection JACK KARGODORIAN
Pre-Inspection 4/17/2025 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 5/14/2025 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 5/14/2025 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 5/15/2025 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 5/15/2025 Approved JACK KARGODORIAN
Pre-Inspection 5/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/26/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 6/26/2025 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 6/26/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ