3319-3323 W 63RD ST 90043
Certificate Information: 3319-3323 W 63RD ST 90043
- Application / Permit
- 23016-10000-11842
- Plan Check / Job No.
- B23LA06984
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: Convert existing attached 4-car garage into a new ADU in (e) duplex per GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 12/4/2023
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2023 | JASON JANGADA |
| Corrections Issued | 4/22/2023 | JASON JANGADA |
| Applicant returned to address corrections | 11/9/2023 | CAROLEAN BASMA |
| Plan Check Approved | 12/3/2023 | CAROLEAN BASMA |
| Issued | 12/4/2023 | APPLICANT |
| CofO in Progress | 12/9/2025 | SALVADOR MARTINEZ |
| No Progress | 12/10/2025 | MICHAEL LEWIS |
| CofO in Progress | 12/10/2025 | MICHAEL LEWIS |
| CofO Issued | 3/24/2026 | DEROLD HAUFF |
| Permit Finaled | 3/24/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2023 | KEVIN AVILA |
| Construction near power lines | Cleared | 8/5/2023 | RIDWAN HARDY |
| "D" conditions | Cleared | 8/17/2023 | SPENCER WEJROWSKI |
| Specific Plan | Cleared | 8/17/2023 | KYLE WINSTON |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 8/20/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Diradourian,, Richard C; Lic. No.: NA10336 | , |
| Contractor | Owner-Builder | , |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: C66727 | 19281 BERCLAIR LANE TARZANA, CA 91356 |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: NA66727 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/23/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 2/23/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Drilled-In Anchors | 2/28/2024 | Conditional Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 2/28/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/5/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 3/5/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/5/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 4/14/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 4/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Rough | 4/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/14/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 5/14/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 5/14/2025 | Approved | WAYNE REGESTER |
| Reinforced Concrete Frame | 5/14/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Insulation | 5/23/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/23/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 6/4/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 6/4/2025 | Approved | WAYNE REGESTER |
| Final | 7/16/2025 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 7/16/2025 | Approved | MICHAEL LEWIS |
| Final | 7/21/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 12/8/2025 | OK to Issue CofO | SALVADOR MARTINEZ |