4553 S GLENCOE AVE 215 90292

Certificate Information: 4553 S GLENCOE AVE 215 90292

Application / Permit
23016-10000-11816
Plan Check / Job No.
B23LA06971
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Doctor's or Dentist's Office
Work Description
CHANGE OF USE FROM OFFICE TO DENTAL OFFICE. no change in parking see comment.
Permit Issued
Issued on 4/18/2024
Issuing Office
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 ARMEN JIVALAGIAN
Corrections Issued 4/25/2023 ARMEN JIVALAGIAN
Quality Review Completed 4/27/2023 PETER KIM
Applicant returned to address corrections 11/15/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/28/2024 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/29/2024 ARMEN JIVALAGIAN
Plan Check Approved 4/16/2024 ARMEN JIVALAGIAN
Issued 4/18/2024 APPLICANT
CofO in Progress 9/30/2025 VASIL MIHALEV
Permit Finaled 10/1/2025 DAVID TSAU
CofO Issued 10/1/2025 DAVID TSAU
Permit Finaled 10/1/2025 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 8/29/2023 DANIEL CORONADO
Miscellaneous Cleared 8/29/2023 DANIEL CORONADO
ZA Case Cleared 8/29/2023 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 11/29/2023 DINAH GARIN
Sewer availability Cleared 12/10/2023 AHMED AMARRAGY
Coastal Zone Cleared 1/3/2024 DALIA MOKAYED
Specific Plan Cleared 1/9/2024 EDUARDO HERMOSO
DAS Clearance Cleared 2/20/2024 Jesse Jimenez

Contact Information

Contractor Espino Roberto; Lic. No.: 924261-B       ,
Contractor Marb Construction Management; Lic. No.: 924261-B       ,
Engineer Feehan,, Matthew D; Lic. No.: C76466 2629 FOOTHILL BLVD STE 146      LA CRESCENTA, CA 91214

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 9/12/2024 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 9/25/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 10/30/2024 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 10/31/2024 Partial Approval GRANT WOODS
Drywall Nailing 12/6/2024 Approved GRANT WOODS
Drywall Nailing 12/24/2024 Approved GRANT WOODS
T-Bar Ceiling 3/20/2025 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 5/15/2025 Approved VASIL MIHALEV
METHANE-Final 8/14/2025 Not Ready for Inspection DERRICK SPENCER
METHANE-Rough 8/14/2025 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 8/14/2025 Not Ready for Inspection DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Approved DERRICK SPENCER
Smoke Detectors 8/14/2025 Not Ready for Inspection DERRICK SPENCER
Final 8/21/2025 Not Ready for Inspection VASIL MIHALEV
Smoke Detectors 8/21/2025 Not Ready for Inspection VASIL MIHALEV
Final 9/16/2025 Not Ready for Inspection VASIL MIHALEV
Smoke Detectors 9/16/2025 Not Ready for Inspection VASIL MIHALEV
Final 9/24/2025 Conditional Approval VASIL MIHALEV
Smoke Detectors 9/24/2025 Approved VASIL MIHALEV
Final 9/30/2025 OK to Issue CofO VASIL MIHALEV