111 S GAFFEY ST 90731

Certificate Information: 111 S GAFFEY ST 90731

Application / Permit
23016-10000-11649
Plan Check / Job No.
B23LA06914
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. PROJECT HOMEKEY: MULTIFAMILY HOUSING PROGRAM PER GCS 50675.1.3. CHANGE OF USE/OCCUPANCY FREOM EXISTING MOTEL (R-1) TO HOMEKEY MULTI-FAMILY HOUSING (R-2) LEVELS 2-3.
Permit Issued
Issued on 9/12/2023
Issuing Office
Current Status
Issued on 9/12/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 KEVIN MORALES
Corrections Issued 5/8/2023 KEVIN MORALES
Quality Review Completed 5/8/2023 EUGENE BARBEAU
Applicant returned to address corrections 6/14/2023 KEVIN MORALES
Plan Check Approved 8/1/2023 KEVIN MORALES
Issued 9/12/2023 APPLICANT

Permit Application Clearance Information

Public Housing Cleared 5/11/2023 JOEL LAUNCHBAUGH
Sewer availability Cleared 5/16/2023 KHAING AYE
Miscellaneous Cleared 5/18/2023 NATHAN ROMINE
Community Plan Implem. Overlay Cleared 5/24/2023 NORALI MARTINEZ
Fire Marshal Fire Life Safety Cleared 6/8/2023 MENOA AGHAJANI
Eng Process Fee Ord 176,300 Cleared 6/13/2023 KHAING AYE
Green Code Cleared 6/13/2023 Rodolfo Arias
Density Bonus Cleared 7/7/2023 MARITES CUNANAN
DAS Clearance Cleared 7/25/2023 Rodolfo Arias

Contact Information

Architect Bardovi,, Gary David; Lic. No.: NA13793       ,
Contractor S V General Contractor Inc; Lic. No.: 986691-B       ,

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2024 Approved JOEY BUCHANAN
Pre-Inspection 4/4/2024 Approved AMANUEL BERHE
Green Building Rough 5/2/2024 Approved JOEY BUCHANAN
Wood Frame 5/2/2024 Partial Approval JOEY BUCHANAN
Wood Frame 5/14/2024 Partial Approval JOEY BUCHANAN
Wood Frame 6/6/2024 Partial Inspection AMANUEL BERHE
Insulation 6/13/2024 Partial Approval JOEY BUCHANAN
Wood Frame 9/19/2024 Partial Inspection AMANUEL BERHE
Drywall Nailing 10/1/2024 Partial Approval JOEY BUCHANAN
Wood Frame 11/1/2024 Corrections Issued JOEY BUCHANAN
Insulation 2/28/2025 Partial Approval JOEY BUCHANAN
Wood Frame 2/28/2025 Partial Approval JOEY BUCHANAN
Final 5/28/2025 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 5/28/2025 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Approved MICHAEL PETRUSKO
Smoke Detectors 5/28/2025 Approved MICHAEL PETRUSKO
Wood Frame 5/28/2025 Approved JOEY BUCHANAN