111 S GAFFEY ST 90731
Certificate Information: 111 S GAFFEY ST 90731
- Application / Permit
- 23016-10000-11648
- Plan Check / Job No.
- B23LA06913
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Motel
- Work Description
- ePLAN. PROJECT HOMEKEY: CHANGE OF USE/OCCUPANCY FROM MOTEL (R1) TO MULTIFAMILY HOUSING PROGRAM (R2) PER GCS 50675.1.3. ALTERATIONS TO BASEMENT AND 1ST FLOOR.
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Current Status
- Issued on 9/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | KEVIN MORALES |
| Corrections Issued | 5/8/2023 | KEVIN MORALES |
| Quality Review Completed | 5/8/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 6/15/2023 | KEVIN MORALES |
| Plan Check Approved | 8/1/2023 | KEVIN MORALES |
| Issued | 9/12/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/16/2023 | KHAING AYE |
| Miscellaneous | Cleared | 5/18/2023 | NATHAN ROMINE |
| Community Plan Implem. Overlay | Cleared | 5/24/2023 | NORALI MARTINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | KHAING AYE |
| Green Code | Cleared | 6/13/2023 | Rodolfo Arias |
| Density Bonus | Cleared | 7/11/2023 | MARITES CUNANAN |
| Public Housing | Cleared | 7/11/2023 | MARITES CUNANAN |
| Fire Marshal Fire Life Safety | Cleared | 7/12/2023 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 7/25/2023 | Rodolfo Arias |
Contact Information
| Architect | Bardovi,, Gary David; Lic. No.: NA13793 | , |
| Contractor | S V General Contractor Inc; Lic. No.: 986691-B | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2024 | Approved | AMANUEL BERHE |
| Wood Frame | 5/2/2024 | Partial Approval | JOEY BUCHANAN |
| Pre-Inspection | 8/9/2024 | Approved | JOEY BUCHANAN |
| Wood Frame | 8/9/2024 | Conditional Approval | JOEY BUCHANAN |
| Special/Order Compliance | 8/21/2024 | Approved | JOEY BUCHANAN |
| Wood Frame | 1/31/2025 | Partial Approval | JOEY BUCHANAN |
| Insulation | 2/13/2025 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 2/19/2025 | Approved | JOEY BUCHANAN |