119 N LARCHMONT BLVD 90004

Certificate Information: 119 N LARCHMONT BLVD 90004

Application / Permit
23016-10000-11636
Plan Check / Job No.
B23LA06911
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Interior Tenant improvement to (E) Retail space. 1st floor, portion of 2nd floor, add elevator to roof and restripe parking lot (no exterior work to occur) URM
Permit Issued
Issued on 11/16/2023
Issuing Office
Current Status
Issued on 11/16/2023

Permit Application Status History

Submitted 4/28/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 HERNAN ARREOLA
Corrections Issued 5/13/2023 HERNAN ARREOLA
Quality Review Completed 5/17/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/12/2023 HERNAN ARREOLA
Applicant returned to address corrections 10/23/2023 HERNAN ARREOLA
Applicant returned to address corrections 10/30/2023 HERNAN ARREOLA
Plan Check Approved 11/15/2023 HERNAN ARREOLA
Issued 11/16/2023 APPLICANT

Permit Application Clearance Information

Encroachment in public way Cleared 8/25/2023 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 8/30/2023 ABEL CASILLAS
"D" conditions Cleared 9/6/2023 HERNAN ARREOLA
"Q" conditions Cleared 9/6/2023 HERNAN ARREOLA
Green Code Cleared 9/22/2023 Fernando Flores
DAS Clearance Cleared 11/9/2023 Fernando Flores
Historic monument Cleared 11/9/2023 MELISSA JONES

Contact Information

Architect Tsoi,, Wing Hung Vincent; Lic. No.: NA23755       ,
Contractor Cooper J D; Lic. No.: 1034515-B       ,
Contractor Dylan & Cooper Inc; Lic. No.: 1034515-B       ,
Engineer Dinari,, Farid; Lic. No.: C38063 61 PLYMOUTH      IRVINE, CA 92620

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2023 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 12/22/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 1/5/2024 Approved JACOB MYERS
Deputy Reinf. Concrete 1/8/2024 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 2/16/2024 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 3/7/2024 Not Ready for Inspection JACOB MYERS
Wood Frame 3/14/2024 Conditional Approval MARTIN TAVITIAN
Insulation 3/28/2024 Partial Approval JACOB MYERS
Final 8/7/2024 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 8/7/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV No Gas LUIS CCAMACHO
Smoke Detectors 8/7/2024 Not Ready for Inspection LUIS CCAMACHO