23301-23303 S HALLDALE AVE 90710

Certificate Information: 23301-23303 S HALLDALE AVE 90710

Application / Permit
23016-10000-11620
Plan Check / Job No.
B23LA06905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) attached Garage to Accessory Dwelling Unit per LAMC 12.22 A33(c)&(e). (448 SQ FT).
Permit Issued
Issued on 7/18/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 ZAW HAN
Corrections Issued 4/25/2023 ZAW HAN
Building Plans Picked Up 4/25/2023 APPLICANT
Applicant returned to address corrections 6/7/2023 MICHAEL LANZONE
Plan Check Approved 7/3/2023 JOSEPH RAFOLS
Issued 7/18/2023 APPLICANT
CofO in Progress 3/8/2024 EUGENE CASSIDY
Permit Finaled 3/8/2024 ANSON MAGLASANG
CofO Issued 3/8/2024 ANSON MAGLASANG
Permit Finaled 3/8/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/15/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 5/15/2023 ANA SORIANO
CPC Cleared 5/16/2023 RYAN LY
Eng Process Fee Ord 176,300 Cleared 5/22/2023 ANA SORIANO
Sewer availability Cleared 6/8/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/8/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/8/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/23/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 10/26/2023 Approved EUGENE CASSIDY
HVAC-Rough 10/26/2023 Approved EUGENE CASSIDY
Insulation 10/26/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 10/26/2023 Approved EUGENE CASSIDY
Drywall Nailing 10/31/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/31/2023 Approved EUGENE CASSIDY
Final 12/14/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 12/14/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 12/14/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 12/14/2023 Approved EUGENE CASSIDY
Final 2/8/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 2/8/2024 Approved EUGENE CASSIDY
Final 2/29/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 3/7/2024 Approved EUGENE CASSIDY
Final 3/7/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/7/2024 Approved EUGENE CASSIDY
PLUMBING-Final 3/7/2024 Approved EUGENE CASSIDY