2115 W 95TH ST 90047

Certificate Information: 2115 W 95TH ST 90047

Application / Permit
23016-10000-11544
Plan Check / Job No.
B23LA06861
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO A DETACHED ADU PER STATE LAW
Permit Issued
Issued on 5/24/2024
Issuing Office
Current Status
CofO Issued on 3/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 4/24/2023 KHUONG TRUONG
Corrections Issued 4/26/2023 KHUONG TRUONG
Plan Check Approved 9/15/2023 CARLOS MONTES
Issued 5/24/2024 APPLICANT
CofO in Progress 2/28/2025 MICHAEL LEWIS
Permit Finaled 3/2/2025 DEROLD HAUFF
CofO Issued 3/2/2025 DEROLD HAUFF
Permit Finaled 3/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2023 KEVIN AVILA
Eng Process Fee Ord 176,300 Cleared 6/20/2023 HUGO LOPEZ
Sewer availability Cleared 6/20/2023 HUGO LOPEZ
Construction near power lines Cleared 8/19/2023 RIDWAN HARDY

Contact Information

Contractor Lozoya General Contractor; Lic. No.: 601290-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2024 Approved JOSE MACIAS
Underground Mechanical 7/10/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 9/10/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 9/10/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 9/10/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 9/17/2024 Conditional Approval AMIR NAZARIAN
HVAC-Rough 9/17/2024 Conditional Approval AMIR NAZARIAN
PLUMBING-Rough 9/17/2024 Approved AMIR NAZARIAN
Deputy Wood Construction 10/3/2024 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 10/7/2024 Approved AMIR NAZARIAN
Green Building Rough 10/7/2024 Corrections Issued AMIR NAZARIAN
METHANE-Rough 10/7/2024 Approved AMIR NAZARIAN
Insulation 10/15/2024 Approved ALEX COLIN
Drywall Nailing 10/22/2024 Partial Approval ALEX COLIN
Interior/Exterior Lathing 10/22/2024 Partial Approval ALEX COLIN
Drywall Nailing 10/24/2024 Approved ALEX COLIN
Interior/Exterior Lathing 10/24/2024 Approved ALEX COLIN
Sewer 12/10/2024 Approved SABAS ALONSO
Underground Mechanical 12/10/2024 Approved SABAS ALONSO
ELECTRICAL-Final 12/31/2024 No Access for Inspection AMIR NAZARIAN
Gas Test 12/31/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 12/31/2024 Corrections Issued AMIR NAZARIAN
Grounding or Bonding 12/31/2024 No Access for Inspection AMIR NAZARIAN
HVAC-Final 12/31/2024 No Access for Inspection AMIR NAZARIAN
PLUMBING-Final 12/31/2024 No Access for Inspection AMIR NAZARIAN
Service/Power Release 12/31/2024 Not Ready for Inspection AMIR NAZARIAN
Verify Rec and Parks Fee Memo 12/31/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 1/23/2025 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Final 1/23/2025 Partial Inspection JOHN QUINTANILLA
Final 1/23/2025 Partial Inspection JOHN QUINTANILLA
Green Building Final 1/23/2025 Partial Inspection JOHN QUINTANILLA
Green Building Rough 1/23/2025 Partial Inspection JOHN QUINTANILLA
HVAC-Final 1/23/2025 Partial Inspection JOHN QUINTANILLA
PLUMBING-Final 1/23/2025 Partial Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 1/23/2025 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Final 2/5/2025 Corrections Issued BARRY HACHE
Green Building Final 2/5/2025 Corrections Issued BARRY HACHE
Smoke Detectors 2/5/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 2/6/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 2/11/2025 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/11/2025 Approved MICHAEL LEWIS
Final 2/11/2025 Partial Inspection MICHAEL LEWIS
Green Building Final 2/11/2025 Corrections Issued MICHAEL LEWIS
Green Building Rough 2/11/2025 Approved MICHAEL LEWIS
HVAC-Final 2/11/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 2/11/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 2/11/2025 Approved MICHAEL LEWIS
Final 2/20/2025 Corrections Issued MICHAEL LEWIS
Green Building Final 2/20/2025 Approved MICHAEL LEWIS
Final 2/27/2025 OK to Issue CofO MICHAEL LEWIS