2115 W 95TH ST 90047
Certificate Information: 2115 W 95TH ST 90047
- Application / Permit
- 23016-10000-11544
- Plan Check / Job No.
- B23LA06861
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 5/24/2024
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | KHUONG TRUONG |
| Corrections Issued | 4/26/2023 | KHUONG TRUONG |
| Plan Check Approved | 9/15/2023 | CARLOS MONTES |
| Issued | 5/24/2024 | APPLICANT |
| CofO in Progress | 2/28/2025 | MICHAEL LEWIS |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2023 | KEVIN AVILA |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 6/20/2023 | HUGO LOPEZ |
| Construction near power lines | Cleared | 8/19/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Lozoya General Contractor; Lic. No.: 601290-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 7/10/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 9/10/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 9/10/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/10/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/17/2024 | Conditional Approval | AMIR NAZARIAN |
| HVAC-Rough | 9/17/2024 | Conditional Approval | AMIR NAZARIAN |
| PLUMBING-Rough | 9/17/2024 | Approved | AMIR NAZARIAN |
| Deputy Wood Construction | 10/3/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/7/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 10/7/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Rough | 10/7/2024 | Approved | AMIR NAZARIAN |
| Insulation | 10/15/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 10/22/2024 | Partial Approval | ALEX COLIN |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 10/24/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/24/2024 | Approved | ALEX COLIN |
| Sewer | 12/10/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 12/10/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/31/2024 | No Access for Inspection | AMIR NAZARIAN |
| Gas Test | 12/31/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 12/31/2024 | Corrections Issued | AMIR NAZARIAN |
| Grounding or Bonding | 12/31/2024 | No Access for Inspection | AMIR NAZARIAN |
| HVAC-Final | 12/31/2024 | No Access for Inspection | AMIR NAZARIAN |
| PLUMBING-Final | 12/31/2024 | No Access for Inspection | AMIR NAZARIAN |
| Service/Power Release | 12/31/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Verify Rec and Parks Fee Memo | 12/31/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| Final | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| Green Building Final | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| Green Building Rough | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| HVAC-Final | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 1/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 2/5/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 2/5/2025 | Corrections Issued | BARRY HACHE |
| Smoke Detectors | 2/5/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 2/6/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 2/11/2025 | Approved | MICHAEL LEWIS |
| Final | 2/11/2025 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 2/11/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 2/11/2025 | Approved | MICHAEL LEWIS |
| HVAC-Final | 2/11/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 2/11/2025 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 2/11/2025 | Approved | MICHAEL LEWIS |
| Final | 2/20/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 2/20/2025 | Approved | MICHAEL LEWIS |
| Final | 2/27/2025 | OK to Issue CofO | MICHAEL LEWIS |