1104-1106 E 8TH ST 90021

Certificate Information: 1104-1106 E 8TH ST 90021

Application / Permit
23016-10000-11450
Plan Check / Job No.
B23LA06821
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Change of use from (E) catering to warehouse
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/26/2023 SHANGQIN XIE
Corrections Issued 4/27/2023 SHANGQIN XIE
Plan Check Approved 7/25/2023 SHANGQIN XIE
Issued 7/26/2023 APPLICANT
Permit Finaled 2/28/2024 ERNESTO CORRAL
CofO Issued 2/28/2024 ERNESTO CORRAL
Permit Finaled 2/28/2024 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 6/21/2023 DALIA MOKAYED
ZA Case Cleared 6/21/2023 DALIA MOKAYED
Historic Resource Verification Cleared 6/26/2023 MAX LODER
Redevelopment Project Area Cleared 6/27/2023 YASMINE BASHIRI
Eng Process Fee Ord 176,300 Cleared 7/19/2023 NEIL TUANO
Sewer availability Cleared 7/19/2023 NEIL TUANO

Contact Information

Contractor A M C Group Inc; Lic. No.: 749575-B       ,
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/29/2023 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/26/2023 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 10/3/2023 Corrections Issued KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 10/10/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 10/10/2023 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Masonry 10/19/2023 Conditional Approval KATY RAMIREZ
Masonry Wall/Backfill 10/20/2023 Approved RAMAZANALI ALMASI
Wood Frame 10/20/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 11/1/2023 Partial Approval RICARDO ROBLES
Deputy Drilled-In Anchors 11/3/2023 Conditional Approval KATY RAMIREZ
Drywall Nailing 11/6/2023 Approved KATY RAMIREZ
Drywall Nailing 11/30/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 11/30/2023 Partial Approval JEROME BLACKWOOD
Final 12/14/2023 Corrections Issued KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 12/14/2023 Approved KATY RAMIREZ
Final 2/26/2024 Partial Approval LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV No Gas LUIS CCAMACHO