1231 N SPRING ST 90012
Certificate Information: 1231 N SPRING ST 90012
- Application / Permit
- 23016-10000-11391
- Plan Check / Job No.
- B23LA06784
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN ; Addition of trellis to at 3rd floor of (e) 5 story office building in common area
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- Issued on 8/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/23/2023 | MOHAMMAD ESMAILI |
| Quality Review Completed | 4/28/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/22/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/29/2023 | MOHAMMAD ESMAILI |
| Issued | 8/4/2023 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 4/20/2023 | MICHAEL AYERS |
| "Q" conditions | Cleared | 4/25/2023 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 5/31/2023 | SHINE LIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | DAVID VO |
| Highway dedication | Cleared | 6/1/2023 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 6/1/2023 | DAVID VO |
| ZA Case | Cleared | 6/2/2023 | GRACIELA ACOSTA |
| Historic monument | Cleared | 6/5/2023 | LAMBERT GIESSINGER |
| Fire Marshal Fire Life Safety | Cleared | 6/13/2023 | WILLIAM JOHNS |
| Metro Rail approval | Cleared | 6/13/2023 | JENNIFER SU |
Contact Information
| Architect | Murnane,, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | G C X Llc; Lic. No.: 1045286-B | 4130 CAHUENGA BLVD NORTH HOLLYWOOD, CA 91602 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 9/8/2023 | Conditional Approval | RAFAEL CORTES |
| Structural Steel Frame | 9/11/2023 | Approved | JULIAN CAPUCETTI |
| Wood Frame | 9/28/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Final | 11/21/2023 | Corrections Issued | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Barrier | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Final | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Rough | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Subgrade | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 11/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 11/21/2023 | Approved | RAMAZANALI ALMASI |
| Final | 12/6/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| METHANE-Barrier | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| METHANE-Final | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| METHANE-Rough | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| METHANE-Subgrade | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 12/6/2023 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | RAMAZANALI ALMASI |
| Final | 5/9/2024 | Corrections Issued | RONALD JIMENEZ |