300 S GRAND AVE LEVEL 2 90071
Certificate Information: 300 S GRAND AVE LEVEL 2 90071
- Application / Permit
- 23016-10000-11360
- Plan Check / Job No.
- B23LA06777
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN. NON-STRUCTURAL TENANT IMPROVEMENT TO 2ND FLOOR OF (E) OFFICE BUILDING.
- Permit Issued
- Issued on 7/5/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2023
Permit Application Status History
| Submitted | 4/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 4/20/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/5/2023 | ANGELICA MARTINEZ |
| No Progress | 7/5/2023 | ANGELICA MARTINEZ |
| Plan Check Approved | 7/5/2023 | ANGELICA MARTINEZ |
| Issued | 7/5/2023 | APPLICANT |
| Permit Finaled | 12/5/2023 | KATY RAMIREZ |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 6/30/2023 | FIRE DEPARTMENT |
Contact Information
| Architect | Maciocia,, Michael Andrew; Lic. No.: NA37656 | , |
| Contractor | Renault And Moran Construction Llc; Lic. No.: 1038156-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/7/2023 | Corrections Issued | KATY RAMIREZ |
| Insulation | 7/10/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 7/10/2023 | Corrections Issued | KATY RAMIREZ |
| Structural Steel Frame | 7/31/2023 | Partial Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 8/8/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| T-Bar Ceiling | 8/10/2023 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 8/14/2023 | Partial Approval | KATY RAMIREZ |
| Special/Order Compliance | 8/29/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 12/1/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 12/1/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 12/1/2023 | Approved | KATY RAMIREZ |
| Final | 12/5/2023 | Permit Finaled | KATY RAMIREZ |