4816 N BRAYTON PL 90041

Certificate Information: 4816 N BRAYTON PL 90041

Application / Permit
23016-10000-11240
Plan Check / Job No.
B23LA06692
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Conversion of an existing storage and laundry room above existing garage to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). No change in footprint and no change in building envelope including height.
Permit Issued
Issued on 9/15/2024
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/17/2023 ADAM HEGAZI
Corrections Issued 4/18/2023 ADAM HEGAZI
Plan Check Approved 5/18/2023 ADAM HEGAZI
No Progress 3/15/2024 ROSENDO MEDINA
Plan Check Approved 3/15/2024 ROSENDO MEDINA
Issued 9/15/2024 APPLICANT
CofO in Progress 3/4/2026 DANIEL DELACRUZ
Permit Finaled 3/26/2026 DANIEL SANCHEZ
CofO Issued 3/26/2026 DANIEL SANCHEZ
Permit Finaled 3/26/2026 DANIEL SANCHEZ

Permit Application Clearance Information

ZA Case Cleared 4/20/2023 DALIA MOKAYED
Address approval Cleared 5/2/2023 DAVID VO
Eng Process Fee Ord 176,300 Cleared 5/2/2023 DAVID VO
Sewer availability Cleared 5/2/2023 DAVID VO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/14/2025 No Access for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 3/14/2025 No Access for Inspection ALIZAH MAYAGOITIA
Wood Frame 3/14/2025 No Access for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/28/2025 Approved PEDRO SIERRA
ELECTRICAL-Rough 3/28/2025 Approved PEDRO SIERRA
Green Building Rough 3/28/2025 Approved PEDRO SIERRA
PLUMBING-Rough 3/28/2025 Approved PEDRO SIERRA
PLUMBING-Rough 4/24/2025 Approved PEDRO SIERRA
Shower Pan 4/24/2025 Approved PEDRO SIERRA
Final 10/22/2025 Not Ready for Inspection DANIEL DELACRUZ
Green Building Final 10/22/2025 Not Ready for Inspection DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Not Ready DANIEL DELACRUZ
Smoke Detectors 10/22/2025 Corrections Issued DANIEL DELACRUZ
Final 11/19/2025 Corrections Issued DANIEL DELACRUZ
Green Building Final 11/19/2025 Approved DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 11/19/2025 Approved DANIEL DELACRUZ
ELECTRICAL-Final 12/16/2025 Approved DANIEL DELACRUZ
Final 12/16/2025 Partial Approval DANIEL DELACRUZ
HVAC-Final 12/16/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Final 12/16/2025 Approved DANIEL DELACRUZ
Final 2/18/2026 Partial Approval DANIEL DELACRUZ
HVAC-Final 2/18/2026 Approved DANIEL DELACRUZ
Final 3/4/2026 OK to Issue CofO DANIEL DELACRUZ