4812 N AVOCA ST 90041
Certificate Information: 4812 N AVOCA ST 90041
- Application / Permit
- 23016-10000-10997
- Plan Check / Job No.
- B23LA06601
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GSC 65852.2(e)(1)(A). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | ROSENDO MEDINA |
| Corrections Issued | 4/17/2023 | ROSENDO MEDINA |
| Plan Check Approved | 5/16/2023 | ARSALAN SHABESTARI |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 12/1/2023 | CRAIG VAUGHAN |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/9/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2023 | TREVOR QUAN |
Contact Information
| Contractor | Golden Point Construction; Lic. No.: 965193-B | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/5/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/29/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 6/29/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/21/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/21/2023 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/21/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 7/26/2023 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 8/2/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 8/2/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/10/2023 | Conditional Approval | BRIAN SULLIVAN |
| Final | 10/12/2023 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 10/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 10/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Pre-Inspection | 10/20/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Green Building Final | 10/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 10/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Final | 10/31/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 10/31/2023 | Approved | CRAIG VAUGHAN |
| Final | 11/1/2023 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Final | 11/1/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Not Required | CRAIG VAUGHAN |
| Smoke Detectors | 11/1/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/30/2023 | Approved | CRAIG VAUGHAN |
| Final | 11/30/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 11/30/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/30/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/30/2023 | Approved | CRAIG VAUGHAN |