708 N MANHATTAN PL 90038

Certificate Information: 708 N MANHATTAN PL 90038

Application / Permit
23016-10000-10750
Plan Check / Job No.
B23LA06508
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Storage Building for Retail Merchandise with office
Work Description
CHANGE OF USE FROM (E) PUBLIC GARAGE TO STORAGE BUILDING FOR RETAIL MERCHANDISE WITH OFFICE, NO CHANGE TO EXISTING STRUCTURE. NO IMPACT TOOLS HOURS OF OPERATION LIMITED FROM 7am TO 11pm
Permit Issued
Issued on 6/13/2023
Issuing Office
Current Status
CofO Issued on 12/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2023 APPLICANT
Assigned to Plan Check Engineer 4/14/2023 SHANGQIN XIE
Corrections Issued 4/15/2023 SHANGQIN XIE
Applicant returned to address corrections 4/27/2023 SHANGQIN XIE
Plan Check Approved 6/3/2023 SHANGQIN XIE
Issued 6/13/2023 APPLICANT
TCO Issued (Expire Date: 09-20-2025) 3/24/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 03-16-2026) 9/17/2025 ERNESTO CORRAL
CofO in Progress 12/5/2025 LUIS CCAMACHO
Permit Finaled 12/5/2025 ERNESTO CORRAL
CofO Issued 12/5/2025 ERNESTO CORRAL
Permit Finaled 12/5/2025 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 5/1/2023 MAX LODER
"D" conditions Cleared 5/23/2023 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 5/23/2023 LOUIS ORTEGA
ZI Cleared 5/23/2023 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 5/26/2023 STEVE MELGAR
Sewer availability Cleared 5/26/2023 STEVE MELGAR
Redevelopment Project Area Cleared 6/1/2023 YASMINE BASHIRI

Contact Information

Architect Raabe,, Evan A; Lic. No.: NA32671       ,
Contractor Mata Contracting Corporation; Lic. No.: 966590-B       ,
Contractor Om Construction; Lic. No.: 966590-B       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/26/2024 Not Ready for Inspection TIMOTHY POWELL
Pre-Inspection 7/26/2024 Approved TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 8/29/2024 Partial Inspection TIMOTHY POWELL
Footing/Foundation/Slab 8/29/2024 Order to Comply Issued TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 9/26/2024 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 10/1/2024 Not Ready for Inspection TIMOTHY POWELL
Light Gage Steel Frame 11/6/2024 Partial Approval TIMOTHY POWELL
Pre-Inspection 2/20/2025 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 8/26/2025 Approved LUIS CCAMACHO
Final 11/12/2025 Not Ready for Inspection TIMOTHY POWELL
Reinforced Masonry Frame 11/12/2025 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved TIMOTHY POWELL
Smoke Detectors 11/12/2025 Approved TIMOTHY POWELL
Final 12/2/2025 OK to Issue CofO LUIS CCAMACHO