3035 W OLYMPIC BLVD 90006
Certificate Information: 3035 W OLYMPIC BLVD 90006
- Application / Permit
- 23016-10000-10704
- Plan Check / Job No.
- B23LA06495
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Veterinary Clinic
- Work Description
- Eplan: Change of use of (e) 2 story, Type IIIB, Furniture store to 2 story Veterinary Clinic.
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | KESETE HAREGOT |
| Corrections Issued | 6/13/2023 | MINA HABIB |
| Quality Review Completed | 6/16/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/12/2023 | MINA HABIB |
| Plan Check Approved | 9/7/2023 | KESETE HAREGOT |
| Issued | 9/13/2023 | APPLICANT |
| CofO in Progress | 1/30/2024 | WINSTON DUNNING |
| Permit Finaled | 1/30/2024 | WINSTON DUNNING |
| CofO Issued | 1/30/2024 | WINSTON DUNNING |
| Permit Finaled | 1/30/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 6/20/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 6/20/2023 | CARTER HOWE |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | CINDY QI |
| Sewer availability | Cleared | 7/10/2023 | CINDY QI |
| DAS Clearance | Cleared | 8/6/2023 | ELIZABETH TOMS |
Contact Information
| Architect | Chun,, Taesik; Lic. No.: C33032 | 520 S GRAND AVENUE SUITE 660 LOS ANGELES, CA 90071 |
| Contractor | Dpt Inc; Lic. No.: 950423-B | 19201 PARTHENIA ST UNIT B NORTHRIDGE, CA 91324 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/26/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Partial Inspection | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 10/4/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Other (see comments) | 10/5/2023 | Conditional Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 10/16/2023 | Approved | RAMAZANALI ALMASI |
| Insulation | 10/19/2023 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 12/1/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 1/11/2024 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Final | 1/11/2024 | Approved | DARRYL ARNOLD |
| METHANE-Rough | 1/11/2024 | Conditional Approval | DARRYL ARNOLD |
| Reinforced Masonry Frame | 1/11/2024 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 1/11/2024 | Approved | DARRYL ARNOLD |