6330 3/4 S BRYNHURST AVE 90043
Certificate Information: 6330 3/4 S BRYNHURST AVE 90043
- Application / Permit
- 23016-10000-10433
- Plan Check / Job No.
- B23LA03892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - convert (e) garage to (n) 1-story ADU per LAMC 12.22 (c)(d)(g) and GCS 65852.2 (e)(1)(D) ADU 2 southside 2 of 2
- Permit Issued
- Issued on 11/8/2023
- Issuing Office
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | KELVIN CHUONG |
| Corrections Issued | 4/6/2023 | KELVIN CHUONG |
| Quality Review Completed | 4/11/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/6/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/24/2023 | KELVIN CHUONG |
| Plan Check Approved | 11/3/2023 | KELVIN CHUONG |
| Plan Check Approved | 11/8/2023 | INTERNET PERMIT |
| Issued | 11/8/2023 | APPLICANT |
| CofO in Progress | 9/8/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/11/2025 | DEROLD HAUFF |
| CofO Issued | 9/11/2025 | DEROLD HAUFF |
| Permit Finaled | 9/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/22/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/22/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 6/13/2023 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 6/16/2023 | TERRY PHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: NA93095 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 12/19/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 4/11/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 5/2/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 6/17/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 8/16/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 8/16/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/22/2024 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 8/22/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Approved | JOSE MACIAS |
| Insulation | 8/30/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/30/2024 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 9/6/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 9/10/2024 | Approved | AMIR NAZARIAN |
| Final | 5/14/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 5/14/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Required | WAYNE REGESTER |
| Smoke Detectors | 5/14/2025 | Approved | WAYNE REGESTER |
| Final | 8/5/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 8/5/2025 | Approved | WAYNE REGESTER |
| Final | 8/15/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 8/19/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 8/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 8/26/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Special/Order Compliance | 8/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/28/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 9/5/2025 | OK to Issue CofO | SALVADOR MARTINEZ |