2150 N BEACHWOOD DR 90068
Certificate Information: 2150 N BEACHWOOD DR 90068
- Application / Permit
- 23016-10000-10421
- Plan Check / Job No.
- B23LA06308
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH.93 USING 4 SHEAR WALLS OF THE TUCK-UNDER PARKING REGION AT NORTH/SOUTH/WEST & EAST OF THE PORTION OF 2 STORY APT.
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/2/2024
Permit Application Status History
| Submitted | 4/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | VARAND SARKISIAN |
| Corrections Issued | 4/17/2023 | VARAND SARKISIAN |
| Quality Review Completed | 4/19/2023 | HANS SANTIAGO |
| Building Plans Picked Up | 4/24/2023 | APPLICANT |
| Plan Check Approved | 6/8/2023 | VARAND SARKISIAN |
| Issued | 6/14/2023 | APPLICANT |
| OK for CofC | 7/2/2024 | WINSTON DUNNING |
| CofC Issued | 7/2/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/30/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2023 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 11/30/2023 | Partial Approval | JACOB MYERS |
| Footing/Foundation/Slab | 4/16/2024 | Partial Inspection | JACOB MYERS |
| Structural Steel Frame | 4/16/2024 | Partial Approval | JACOB MYERS |
| Wood Frame | 4/16/2024 | Partial Approval | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 5/8/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/7/2024 | Conditional Approval | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 6/7/2024 | Approved | JACOB MYERS |
| Final | 6/24/2024 | Conditional Approval | JACOB MYERS |
| Final | 6/28/2024 | Partial Inspection | WINSTON DUNNING |
| Final | 7/2/2024 | OK for CofC | WINSTON DUNNING |