712 N SEWARD ST 90038

Certificate Information: 712 N SEWARD ST 90038

Application / Permit
23016-10000-10397
Plan Check / Job No.
B23LA06299
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan. Tenant Improvement in an exisitng building that includes new construction of a projection room, sound lock, and private screening room. Project includes new mechanical systems. No change to building core system. TI Scope 749.5 SF. See comment.
Permit Issued
Issued on 6/22/2023
Issuing Office
Current Status
Permit Finaled on 4/10/2024

Permit Application Status History

Submitted 4/7/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 TSE MING HUANG
Corrections Issued 4/18/2023 TSE MING HUANG
Quality Review Completed 4/20/2023 EUGENE BARBEAU
Plan Check Approved 6/9/2023 TSE MING HUANG
Issued 6/22/2023 APPLICANT
Permit Finaled 4/10/2024 TIMOTHY POWELL

Permit Application Clearance Information

DAS Clearance Cleared 5/23/2023 Fernando Flores

Contact Information

Architect Brennan,, Ross A; Lic. No.: C27858 7008 SANTA MONICA BLVD      HOLLYWOOD, CA 90038
Contractor Warner Constructors Llc; Lic. No.: 528146-B       ,
Engineer Smith,, Chris Wayne; Lic. No.: S6106 1852 CORINTH AVE #11      LOS ANGELES, CA 90025

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/20/2023 Approved RONALD JIMENEZ
Drywall Nailing 9/28/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 9/28/2023 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 10/2/2023 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 10/7/2023 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 10/7/2023 Off-Hour Fees Due
Footing/Foundation/Slab 10/10/2023 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 10/25/2023 Approved RONALD JIMENEZ
Insulation 11/20/2023 Approved JACOB MYERS
Structural Steel Frame 11/22/2023 Not Ready for Inspection RONALD JIMENEZ
Wall Anchors 11/22/2023 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 11/22/2023 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 11/29/2023 Partial Approval LUIS CCAMACHO
Drywall Nailing 12/6/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 12/6/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 12/11/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 12/20/2023 Partial Approval GREGORY POMISH
Drywall Nailing 12/21/2023 Partial Approval GREGORY POMISH
Drywall Nailing 1/6/2024 Off-Hour Fees Due
Drywall Nailing 1/6/2024 Partial Approval ALFREDO LOPEZ
T-Bar Ceiling 1/6/2024 Off-Hour Fees Due
T-Bar Ceiling 1/6/2024 Partial Approval ALFREDO LOPEZ
Final 3/8/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 3/8/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 3/8/2024 Not Ready for Inspection LUIS CCAMACHO
Pre-Inspection 3/20/2024 Partial Approval LUIS CCAMACHO
Special/Order Compliance 3/20/2024 Off-Hour Fees Due
Final 4/4/2024 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 4/4/2024 Approved TIMOTHY POWELL
Final 4/10/2024 Permit Finaled TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved TIMOTHY POWELL