4224 S LINCOLN BLVD 90292

Certificate Information: 4224 S LINCOLN BLVD 90292

Application / Permit
23016-10000-10241
Plan Check / Job No.
B23LA06199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Grocery Store
Work Description
TENANT IMPROVEMENT FOR CHANGE OF USE FROM (E) RETAIL SPACE TO GROCERY STORE. SCOPE TO INCLUDE NEW PARTITIONS, NEW FINISHES, EQUIPMENT, AND NEW SINK.
Permit Issued
Issued on 7/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 AUNG SOE
Corrections Issued 4/18/2023 AUNG SOE
Building Plans Picked Up 4/20/2023 APPLICANT
Applicant returned to address corrections 6/2/2023 LUKE GONZALES
Plan Check Approved 7/21/2023 SAMUEL GONZALEZ
Issued 7/24/2023 APPLICANT
CofO in Progress 12/27/2023 GRANT WOODS
Permit Finaled 12/27/2023 DAVID TSAU
CofO Issued 12/27/2023 DAVID TSAU
Permit Finaled 12/27/2023 DAVID TSAU

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 4/27/2023 NOAH MCCOY
Specific Plan Cleared 5/31/2023 FREDDY GARCIA
Food establishment approval Cleared 6/2/2023 LACDHS APPROVED
Sewer availability Cleared 6/6/2023 WALLIE JONG
Specific Plan Cleared 7/19/2023 FREDDY GARCIA
"Q" conditions Cleared 7/20/2023 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 7/20/2023 WALLIE JONG

Contact Information

Contractor Zingo Construction; Lic. No.: 969638-B 390 HAUSER BLVD APT 6K      LOS ANGELES, CA 90036

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 9/13/2023 Corrections Issued GRANT WOODS
Wood Frame 9/26/2023 Not Ready for Inspection GRANT WOODS
Final 10/24/2023 Not Ready for Inspection AMANUEL BERHE
METHANE-Final 10/24/2023 Approved AMANUEL BERHE
METHANE-Rough 10/24/2023 Approved AMANUEL BERHE
Reinforced Masonry Frame 10/24/2023 Approved AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready AMANUEL BERHE
Smoke Detectors 10/24/2023 Approved AMANUEL BERHE
Wood Frame 10/24/2023 Not Ready for Inspection AMANUEL BERHE
Final 11/13/2023 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved GRANT WOODS
Final 11/20/2023 Not Ready for Inspection GRANT WOODS
Final 12/8/2023 Partial Inspection DAVID TSAU
Final 12/12/2023 Not Ready for Inspection ALAN NOVAK
Pre-Inspection 12/13/2023 Approved ALAN NOVAK
Final 12/22/2023 Conditional Approval GRANT WOODS
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved GRANT WOODS
Smoke Detectors 12/22/2023 Approved GRANT WOODS