705-707 N ROSEMONT AVE 90026
Certificate Information: 705-707 N ROSEMONT AVE 90026
- Application / Permit
- 23016-10000-10169
- Plan Check / Job No.
- B23LA06178
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: CONVERT (E) 2 STORY SFD INTO A DUPLEX.
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/11/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 2/16/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/20/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/27/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/28/2024 | LUISANGEL VALENZUELA |
| Issued | 4/2/2024 | APPLICANT |
| CofO in Progress | 10/21/2024 | FREDDIE RIVERA |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
| CofO Issued | 10/28/2024 | RUBEN SALAS |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 6/29/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2024 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 5/21/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/4/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 6/4/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/4/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/18/2024 | No Access for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 6/21/2024 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 8/5/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/9/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/13/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/13/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 9/13/2024 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Final | 9/13/2024 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 9/13/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 9/13/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/13/2024 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/13/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | FREDDIE RIVERA |
| Final | 10/15/2024 | OK to Issue CofO | FREDDIE RIVERA |
| MERV13>=Final | 10/15/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 10/15/2024 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 10/15/2024 | Approved | FREDDIE RIVERA |