1148 1/2 S DOHENY DR 90035
Certificate Information: 1148 1/2 S DOHENY DR 90035
- Application / Permit
- 23016-10000-10131
- Plan Check / Job No.
- B23LA06159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE ATTACHED TO APARTMENT TO AN ADU ADU CHECKED PER CA COVT. CODE 65852.2(E)(1)(C)
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Metro
- Current Status
- Issued on 11/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | SUNMIN LEE |
| Corrections Issued | 4/8/2023 | SUNMIN LEE |
| Quality Review Completed | 4/12/2023 | KEN GILL |
| Building Plans Picked Up | 4/17/2023 | APPLICANT |
| Green Plans Picked Up | 4/24/2023 | APPLICANT |
| Applicant returned to address corrections | 9/29/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 10/19/2023 | SUNMIN LEE |
| Plan Check Approved | 11/20/2023 | SUNMIN LEE |
| Issued | 11/28/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/2/2023 | DARIN LAM |
| Address approval | Cleared | 8/3/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | DARIN LAM |
| Tenant Habitability Plan | Cleared | 9/7/2023 | ISMAEL HERNANDEZ |
| DAS Clearance | Cleared | 9/13/2023 | SUNMIN LEE |
| Green Code | Cleared | 9/18/2023 | AARON COSTA |
| SB8 RUD | Cleared | 11/8/2023 | HUGO GARRIDO GARZA |
| Grading Pre-Inspection | Cleared | 11/20/2023 | SUNMIN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/9/2024 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 5/20/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 8/20/2025 | Approved | FARHAD DADBIN |
| Drywall Nailing | 9/16/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Rough | 9/16/2025 | Approved | FARHAD DADBIN |
| Insulation | 9/29/2025 | Partial Approval | FARHAD DADBIN |
| METHANE-Rough | 1/14/2026 | Approved | FARHAD DADBIN |
| Wood Frame | 1/14/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Drywall Nailing | 3/3/2026 | Approved | FARHAD DADBIN |