4323 1/2 N GENTRY AVE 91604

Certificate Information: 4323 1/2 N GENTRY AVE 91604

Application / Permit
23016-10000-10086
Plan Check / Job No.
B23LA06123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (E) 323 SQ FT DETACHED GARAGE CONVERTED TO ADU PER CA Govt. Code 65852.2(e)(1)(A) , NO SQFT ADDED
Permit Issued
Issued on 5/11/2024
Issuing Office
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 KHUONG TRUONG
Corrections Issued 4/12/2023 KHUONG TRUONG
Applicant returned to address corrections 8/22/2023 HANS SANTIAGO
Plan Check Approved 8/29/2023 ANDREW SANTIAGO
Issued 5/11/2024 APPLICANT
CofO in Progress 4/2/2026 JAVIER RAMOS JR
Permit Finaled 5/11/2026 RUBEN SALAS
CofO Issued 5/11/2026 RUBEN SALAS
Permit Finaled 5/11/2026 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 4/21/2023 STEVEN WECHSLER
Address approval Cleared 4/22/2023 CARLOS AGUILERA
Sewer availability Cleared 4/22/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/26/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/26/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 6/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 6/26/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 7/19/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/7/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 9/9/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/9/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/17/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/17/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/28/2024 Partial Approval DAVID MATSON
Green Building Rough 10/28/2024 Approved DAVID MATSON
HVAC-Rough 10/28/2024 Approved DAVID MATSON
Insulation 11/4/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Conditional Approval CHRISTOPHER ROJAS
Sewer 11/19/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/1/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 4/1/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/29/2025 Approved JAVIER RAMOS JR
Drywall Nailing 4/29/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/29/2025 Approved JAVIER RAMOS JR
Shower Pan 4/29/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/13/2026 Corrections Issued JAVIER RAMOS JR
Final 3/13/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/13/2026 Approved JAVIER RAMOS JR
HVAC-Final 3/13/2026 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 3/13/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 3/13/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/1/2026 Approved JAVIER RAMOS JR
Final 4/1/2026 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 4/1/2026 Approved JAVIER RAMOS JR
Service/Power Release 4/23/2026 Approved JAVIER RAMOS JR