8605 N CEDROS AVE 1-6 91402
Certificate Information: 8605 N CEDROS AVE 1-6 91402
- Application / Permit
- 23016-10000-10058
- Plan Check / Job No.
- B23LA06109
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) STORAGE ROOMS TO ADU IN EXISTING 2 STORY APARTMENT BUILDING per State Law, CA Govt. Code 65852.2(e)(1)(C) - No structural change
- Permit Issued
- Issued on 8/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2023 | AUNG SOE |
| Corrections Issued | 4/10/2023 | AUNG SOE |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Applicant returned to address corrections | 6/29/2023 | MINA HABILI |
| Plan Check Approved | 6/30/2023 | KHUONG TRUONG |
| Issued | 8/7/2023 | APPLICANT |
| CofO in Progress | 8/23/2024 | ANDREW DORSO |
| Permit Finaled | 8/23/2024 | JEFFREY DURAN |
| CofO Issued | 8/23/2024 | JEFFREY DURAN |
| Permit Finaled | 8/23/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/22/2023 | DAGOVERTO GUERRERO |
| Tenant Habitability Plan | Cleared | 6/6/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Kunyoung; Lic. No.: C66880 | 22812 ERIEL AVE TORRANCE, CA 90505 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2023 | Partial Inspection | ANDREW DORSO |
| Insulation | 5/14/2024 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 5/31/2024 | Approved | ANDREW DORSO |
| Wood Frame | 5/31/2024 | Approved | ANDREW DORSO |
| Insulation | 6/11/2024 | Approved | ANDREW DORSO |
| Drywall Nailing | 6/20/2024 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 6/26/2024 | Approved | ANDREW DORSO |
| Final | 8/20/2024 | OK to Issue CofO | ANDREW DORSO |
| Green Building Final | 8/20/2024 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 8/20/2024 | Approved | ANDREW DORSO |