3230 S OVERLAND AVE 90034

Certificate Information: 3230 S OVERLAND AVE 90034

Application / Permit
23016-10000-10057
Plan Check / Job No.
B23LA06106
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
STRUCTURAL REPAIRS TO DAMAGED ROOF. NO CHANGE IN AREA. ALL WORK DONE PER ENGINEERING
Permit Issued
Issued on 6/5/2024
Issuing Office
West Los Angeles
Current Status
Issued on 6/5/2024

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/4/2023 DANIEL SMILEY
Corrections Issued 4/4/2023 DANIEL SMILEY
Plan Check Approved 3/15/2024 ZAW HAN
Issued 6/5/2024 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 8/15/2023 KYLE WINSTON
Tenant Habitability Plan Cleared 3/5/2024 RICARDO BOHORQUEZ
Building over 36-ft Cleared 3/15/2024 CALOSHA APPROVED

Contact Information

Contractor Collaborative Construction Inc; Lic. No.: 956472-B 5212 1/2 FOUNTAIN AVENUE 3      LOS ANGELES, CA 90029
Engineer Coray,, Jason Gregory; Lic. No.: S4926 56 OAK SPRINGS DR      SAN ANSELMO, CA 94930

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 11/7/2024 Not Ready for Inspection FARHAD DADBIN
Wood Frame 11/18/2024 Approved DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Approved DANIEL VARNUM
Insulation 11/20/2024 Approved DANIEL VARNUM
Interior/Exterior Lathing 12/10/2024 Partial Approval FARHAD DADBIN
Wood Frame 12/10/2024 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 12/18/2024 Partial Approval FARHAD DADBIN
Wood Frame 1/23/2025 Partial Approval FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Partial Approval FARHAD DADBIN
Wood Frame 2/4/2025 Partial Approval FARHAD DADBIN
Wood Frame 3/25/2025 Partial Approval FARHAD DADBIN
Wood Frame 4/1/2025 Partial Approval VASIL MIHALEV
Wood Frame 4/15/2025 Partial Approval FARHAD DADBIN
Wood Frame 4/30/2025 Partial Approval FARHAD DADBIN
Wood Frame 10/2/2025 Partial Approval FARHAD DADBIN
Insulation 10/3/2025 Partial Approval FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval FARHAD DADBIN