3818 S BERRYMAN AVE 90066

Certificate Information: 3818 S BERRYMAN AVE 90066

Application / Permit
23016-10000-09989
Plan Check / Job No.
B23LA06049
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Convert Existing Garage (380sf) and Rec room(250sf) to ADU (630sf) Per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/6/2023
Issuing Office
Current Status
CofO Issued on 2/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 ZAW HAN
Corrections Issued 4/12/2023 ZAW HAN
Applicant returned to address corrections 5/18/2023 ZAW HAN
Applicant returned to address corrections 5/25/2023 ZAW HAN
Plan Check Approved 5/26/2023 RICARDO RAMIREZ
Issued 6/6/2023 APPLICANT
CofO in Progress 1/9/2024 RYAN BARNES
Permit Finaled 2/8/2024 BRUCE TODD
CofO Issued 2/8/2024 BRUCE TODD
Permit Finaled 2/8/2024 BRUCE TODD

Permit Application Clearance Information

CPC Cleared 4/13/2023 MAXFIELD VERMY
CPC Cleared 4/13/2023 MAXFIELD VERMY
Address approval Cleared 4/17/2023 DARIN LAM
Roof/Waste drainage to street Cleared 4/17/2023 DARIN LAM
Sewer availability Cleared 4/17/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 4/25/2023 DARIN LAM
Specific Plan Cleared 4/26/2023 JIMMY VIVAR

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/28/2023 Approved RYAN BARNES
Pre-Inspection 7/19/2023 Partial Approval RYAN BARNES
Pre-Inspection 7/25/2023 Partial Approval RYAN BARNES
Pre-Inspection 8/1/2023 Not Ready for Inspection RYAN BARNES
Footing/Foundation/Slab 8/15/2023 Approved RYAN BARNES
PLUMBING-Rough 8/15/2023 Partial Approval RYAN BARNES
Deputy Drilled-In Anchors 9/7/2023 Approved JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval RYAN BARNES
ELECTRICAL-Rough 9/18/2023 Partial Approval RYAN BARNES
PLUMBING-Rough 9/18/2023 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 9/19/2023 Approved RYAN BARNES
PLUMBING-Rough 9/19/2023 Approved RYAN BARNES
Insulation 9/20/2023 Not Ready for Inspection RYAN BARNES
Insulation 9/26/2023 Approved RYAN BARNES
ELECTRICAL-Rough 9/29/2023 Not Ready for Inspection RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved RYAN BARNES
Drywall Nailing 10/19/2023 Approved JOHN MATTILLO
Shower Pan 10/30/2023 Approved RYAN BARNES
Interior/Exterior Lathing 11/3/2023 Approved JOHN MATTILLO
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Not Ready RYAN BARNES
ELECTRICAL-Final 12/14/2023 Corrections Issued RYAN BARNES
Final 12/14/2023 Not Ready for Inspection RYAN BARNES
HVAC-Final 12/14/2023 Corrections Issued RYAN BARNES
PLUMBING-Final 12/14/2023 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Not Ready RYAN BARNES
Smoke Detectors 12/14/2023 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 1/4/2024 Approved RYAN BARNES
Final 1/4/2024 Conditional Approval RYAN BARNES
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved RYAN BARNES
Service/Power Release 1/4/2024 Approved RYAN BARNES
Smoke Detectors 1/4/2024 Approved RYAN BARNES